Hello @Rbby1015 there is no direct way to do budgetory control on PR/PO you need to use CO account assigment like internal order/cost center, same can be assigned in related PO/PR & used for budgetory purpose.Regards,Sumesh Gupta
Hello Satish if you change it to warning message system will not stop user in MIGO/ML81N even if no budget available.For budget profile & availalibity control refer below blog.https://community.sap.com/t5/enterprise-resource-planning-blogs-by-members...
Hi @vishaldev85 it seems YYY is not correct naming convention double click on error & see what namespace is permitted create accordingly.RegardsSumesh Gupta
Hello Satish, if you just want to remove error & no budgetory control needed for orders then u can turn off the availibity control for the bugget profile assigned to internal order type or can change message to warning in same configuration.Regards,S...