Supply Chain Management Blogs by Members
Learn about SAP SCM software from firsthand experiences of community members. Share your own post and join the conversation about supply chain management.
cancel
Showing results for 
Search instead for 
Did you mean: 
SaikiranGummadi
Participant

Introduction:

Now a days multiple warehouses are connected to a single plant where stock transfer happens from one storage location to another storage location which helps in efficient procurement strategies. Here we can usually post without value since the transferred material is managed with in the same plant and therefore has the same valuation data as before. In this blog post, I will be discussing Intra Company STO with in the plant between two EWM managed warehouses i.e. supplying as well as receiving plant are same.

We can Transfer the goods between Storage locations in two ways:

  • Without Shipping Point in the Purchase Order, we can transfer the goods/products by using MM – STO. (Without Delivery and Without Billing)
  • With Shipping Point in the Purchase Order, we must maintain some Configurations Settings. (With Delivery and Without Billing)

Configuration:

  • Define Shipping Data for Plants
  • Configure Delivery Type & Availability Check Procedure by Plant
  • Assign Document Type, One-Step Procedure, Underdelivery Tolerance
  • Activate Stock Transfer Between Storage Locations
  • Assign Delivery Type and Checking Rule According to Storage Location
  • Define Shipping Data for Stock Transfers Between Storage Locations
  • Define Rule for Determination of Shipping Point
  • Assign Shipping Points According to Storage Location
  • Assign Warehouse Number to Plant and Storage Location
  • Assign Warehouse Numbers from Logistics Execution
  • Map Storage Locations from ERP System to EWM

STO FLOW:

  • Create PO in the supplying plant (here supplying and receiving plants are same)
  • Create outbound Delivery in VL10B.
  • Check for the available stock in the Storage location.
  • Go to Outbound Delivery Request of the supplying plant warehouse & complete GI process.
  • Check for the stock in the supplying plant which must have been reduced.
  • Check for the Inbound delivery number which got generated automatically in the background w.r.t outbound.
  • Then go to inbound delivery request and complete the WH process in the receiving plant.
  • Check for the stock report in the receiving plant.


Below mentioned three steps are mandatory fields to obtain the shipping tab in the PO:

  • Define Shipping Data for Plants
  • Configure Delivery Type & Availability Check Procedure by Plant
  • Assign Document Type, One-Step Procedure, Under delivery Tolerance

These are the mandatory steps we need to maintain to get the shipping tab.

Configuration Path:

Define Shipping Data for Plants:

SPRO –> IMG –> Material Management –> Purchasing –> Purchase order –> Set up Stock Transport order –> Define Shipping Data for Plants

We can assign the customer in the supplying Plant for this process. (i.e., the supplying and Receiving Plant are same for this process.)

saikiran_0910_0-1706699498662.png

Configure Delivery Type & Availability Check Procedure by Plant:

SPRO –> IMG –> Material Management –> Purchasing –> Purchase order –> Set up Stock Transport order –> Assign Delivery Type and Checking Rule

saikiran_0910_1-1706699498669.png

Assign Document Type, One-Step Procedure, under delivery Tolerance:

SPRO –> IMG –> Material Management –> Purchasing –> Purchase order –> Set up Stock Transport order –> Assign Document Type, One-Step Procedure, Under delivery Tolerance

saikiran_0910_2-1706699498680.png

Activate Stock Transfer Between Storage Locations:

SPRO –> IMG –> Material Management –> Purchasing –> Purchase Order –>Set up Stock Transport Order–>Set Up Stock Transfer Between Storage Locations–>Activate Stock Transfer Between Storage Locations

saikiran_0910_3-1706699498686.png

Configure Delivery Type & Availability Check Procedure by Storage Location:

SPRO –> IMG –> Material Management –> Purchasing –> Purchase Order –> Set up Stock Transport Order –> Set Up Stock Transfer Between Storage Locations –>Configure Delivery Type & Availability Check Procedure by Storage Location

In this Step we can maintain

  • Purchase document category 'F' , here use PO type UB, supplying plant, issue storage location and delivery type(prefer to create new delivery type by copying delivery type 'NL' replenish delivery.)

saikiran_0910_4-1706699498690.png

In this step we can create new delivery type by copying from the standard delivery type.

SPRO –>IMG –> Logistics Execution –> Shipping –> Deliveries –>Define Delivery Types

Here I create the new delivery Type as “SL” by copying from the standard one “NL”.

saikiran_0910_5-1706699498693.png

Here I am assigning the Supplying Plant, Supplying storage location and Delivery Type to Document Type.

saikiran_0910_6-1706699498703.png

Define Shipping Data for Stock Transfers Between Storage Locations:

SPRO –> IMG –> Material Management –> Purchasing –> Purchase Order –> Set up Stock Transport Order –> Set Up Stock Transfer Between Storage Locations –>Define Shipping Data for Stock Transfers Between Storage Locations

In this step we can assign Sales organization, Distribution Channel, Shipping Point and Division to the Plant and later select the Plant and click on the Storage location.

saikiran_0910_7-1706699498707.png

By maintaining the data click on the save button.

saikiran_0910_8-1706699498715.png

Define Rule for Determination of Shipping Point:

SPRO –> IMG –> Logistics Execution –>Shipping –> Basic Shipping Functions –>Shipping Point and Goods Receiving Point Determination–>Set Up Storage-Location-Dependent Shipping Point Determination–>Define Rule for Determination of Shipping Point

saikiran_0910_9-1706699498719.png

Assign Shipping Points According to Storage Location:

SPRO –> IMG –> Logistics Execution –> Shipping –> Basic Shipping Functions –>Shipping Point and Goods Receiving Point Determination –>Set Up Storage-Location-Dependent Shipping Point Determination –>Assign Shipping Points According to Storage Location

saikiran_0910_10-1706699498723.png

Assign Warehouse Number to Plant and Storage Location:

SPRO –> IMG –> Enterprise Structure –> Assignment –> Logistics Execution–>  Assign Warehouse Number to Plant and Storage Location

saikiran_0910_11-1706699498725.png

Assign Warehouse Numbers from Logistics Execution

SPRO –> IMG –> SCM Extended Warehouse Management–> Extended Warehouse Management–> Interfaces –> ERP Integration –> General Settings –> Assign Warehouse Numbers from Logistics Execution

saikiran_0910_12-1706699498730.png

Map Storage Locations from ERP System to EWM

SPRO –> IMG –> SCM Extended Warehouse Management–> Extended Warehouse Management–> Interfaces –> ERP Integration –> Goods Movements–> Map Storage Locations from ERP System to EWM

saikiran_0910_13-1706699498738.png

Testing:

 

 

Details

Supplying Plant

Receiving Plant

1

Plant

5PL1

5PL1

2

Warehouse no

5EWM

4EWM

3

Product

7243

7243

4

Shipping point

5SP1

5SP1

5

Purchase organization

5POR

 

6

Customer

1029900577

 

7

Sales Area (Sorg/D.ch/Div)

5SPO/01/01

 

8

Storage Location

AFS

AFS1

 

 

ECC Delivery type

ECC Item Category

EWM Doc Category

EWM Doc type

EWM Item type

EWM Item Category

Outbound

SL

NLN

PDO

OUTB

ODLV

DLV

Inbound

EL

ELN

PDI

INB

IDLV

DLV

Step:1

Now create the Material.

Material – 7244

saikiran_0910_14-1706699498762.png

Step:2

The Material is Extended to both Storage locations in MMSC.

Step:3

Now Create the Purchase Order in ME21N:

  • Document Type – UB
  • Enter Supplying Plant – 5PL1
  • Enter PO Creating Storage Location and Material Issuing Storage location.
  • As you can see in the Item Details the Shipping Tab is triggered which is mandatory for STO process.

saikiran_0910_15-1706699498790.png

Stock Transp. Order created under the number 4500006531.

Step 4:

Check the stock in Stock overview in MMBE.

  • We have 100 Quantity in Plant – 5PL1 and Storage location AFS.

saikiran_0910_16-1706699498793.png

Step 5:

Here I am creating the Outbound Delivery in VL10B Transaction Code.

  • Enter the Shipping Point and Purchase order Number and click on Execute Button.

saikiran_0910_17-1706699498797.png

Select the PO Number and click on the Background button.

saikiran_0910_18-1706699498800.png

Another line will be generated with Green Mark. Select that line and click on the Delivery log creation Tab.

saikiran_0910_19-1706699498805.png

Place the Cursor and click on the documents button the Outbound Delivery Number will be displayed.

saikiran_0910_20-1706699498808.png

The Outbound Delivery Number is – 80004086.

saikiran_0910_21-1706699498810.png

Step 6:

Check the delivery with Plant and storage location got triggered and successfully distributed to EWM  in VL02N

saikiran_0910_22-1706699498825.png

Step 7:

Go to /N/SCWM/PRDO

saikiran_0910_23-1706699498838.png

Create the warehouse task and confirm the warehouse task

saikiran_0910_24-1706699498847.png

saikiran_0910_25-1706699498848.png

Confirm the warehouse order

saikiran_0910_26-1706699498855.png

After clicking on the Goods Issue the Status changed to “Completed” and Outbound delivery was generated

saikiran_0910_27-1706699498862.png

Step :8

We have maintained Output type SPED to  trigger inbound delivery after GoodsIssue has been completed for intra-company STO's outbound delivery 

saikiran_0910_28-1706699498865.png

Step 9:

Check the stock has deducted from the AFS storage location in MMBE

saikiran_0910_29-1706699498870.png

Step:10

Check for the PO history using ME23N & can check the Outbound delivery number in the Reference column i.e. 80004086

saikiran_0910_30-1706699498876.png

Step:11

Check the inbound delivery got created with reference to reference to outbound delivery in the PO confirmations tab

saikiran_0910_31-1706699498887.png

Step:12

Check the inbound delivery in VL32N whether it is successfully distributed to EWM or not.

saikiran_0910_32-1706699498904.png

Step:13

Go to /N/SCWM/PRDI and process the delivery

saikiran_0910_33-1706699498920.png

Create the warehouse task and confirm the warehouse task

saikiran_0910_34-1706699498942.png

Confirm the warehouse order

saikiran_0910_35-1706699498961.png

Step:14

Check the stock in MMBE for material 7244 in AFS1 storage location

saikiran_0910_36-1706699498964.png

Conclusion:
This blog post walks you through the creation of the Intra STO with in the plant process and the key parameters that need to be checked and referred to while performing an Intra STO with in the plant between Two EWM managed warehouses and various steps involved in performing the scenario.

Thank you for reading the post, please share thoughts and feedback.

This is my personal observation based on requirements I worked on, and this blog is based on S4 HANA 2020 version sandbox.
Reference-

Some of the blog posts can be referred to in the forum for the STO process to trigger the output type for inbound delivery

https://community.sap.com/t5/enterprise-resource-planning-blogs-by-members/output-type-sped-trigger-...

 

Labels in this area