Hello Experts,
We have scenario, where we have two materials and both have status of obsolete. These are externally procured material with Procurement type as 'F' and having the MRP type as 'PD' and lot size as Period lot size. We have maintained minimum lot size as 1620000 and rounding value as 1620000 for both materials. When we run MRP Live for the plant with planning mode as '3' 'delete and recreate' it creates the PR for one material with quantity 1620000 an for other its not creating any PR. I have checked master data for both materials and its exactly same, still why system is behaving like this. Can you provide details what other things I have to check.
Pls suggest the options other than ND MRP type.
Hi Arjuna,
I thought about this and started to search for PR created date but I couldn't. Can you tell me where I can find PR created date.
Also why MRP has created PR only for single material and not for other. We have obsolete both materials on same day.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
10 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.