Hi All

I want to change the customization in the pm work confirmation so that the “final confirmation” flag will not be on automatically. So that there will not be a warning massage every time I want to add confirmation on activity that has actual work document (since my users will not turn off the flag in case they didn’t finish the work)

As a result I will probably have PM order that the work was completed; I want to close, but the system status is still PCNF Partially confirm.

Is that a problem?

If I don’t use the flag to really know if the work was really completed, can I keep it always as partially confirmed until I do TECO and business completion?

Thanks

Irit

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Irit,

The PM order confirmation you are referring is a SRM confirmation created to a PO in ECC? Could you clarify your requirement in SRM confirmation by attaching screenshots?

Best Regards,

Guilherme Montagner