on 12-05-2022 7:50 PM
Dear all,
following situation :
We have a original production order with 5 operations and 10 Pieces.
010 OP01
020 OP02
030 OP03
040 OP04
050 OP05
After confirming 10 pieces in OP04 the quality check makes it neccessary to create a rework order for the steps OP02 , OP03 and OP04 for these 10 pieces. We create a rework order (CO07) with these 3 operations and confirm the rework order. Is there any possibilty that OP05 from the original order only starts when rework order is confirmed.
Thanks for your help.
Chistian