The bw extractor 2LIS_04_P_COMP is extracting values for field BDMNG in BW system. But for any goods movement done in the ECC source system for any process order, the datasource extracts data in BW but the field BDMNG has repeated values of Requriement Qty for all line items generated.

The total of this field for a process order is therefore wrong and is not matching with the ECC system. Please provide help.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

maggie_yi
Advisor
Advisor
0 Kudos

Hi Shalabh Jain,

Is this note installed:

2696699 - Requirement Quantity doubles in S026 after goods issue to a production order.

If not, please apply it.

Best regards,
Maggie