cancel
Showing results for 
Search instead for 
Did you mean: 

LOSC not working for Combined Put away for HU with Multiple Items

mukesh_s26
Explorer
0 Kudos

Hello Team,

Currently we are having a requirement where HU for Prime should be routed to direct combined put away if the number of items is 5 for prime activity area and anything more than 5 should route to the deconsolidation station.

We are able to route the HUs more than 5 to Decon and less than or equal to 5 to put away. But we have a pre put away interim bin which is in between staging and put away.

For direct put away, HUs should be routed to interim pre put away and then to the final put away. This setting we have done using the LOSC.

POSC:

LOSC:

But the Losc setting is not working and hu is not routed to interim bin. We have go through KBA and tried same options with pick control but that also not working

2649697 - LOSC is not considered at WT creation .

We have gone through routing code and standard is checking the moveHU field to proceed for the LOSC or not. Kindly let us know if routing HU with multiple lines to interim bins before put away through LOSC is possible or not in standard.

Thanks

Mukesh.S

Accepted Solutions (0)

Answers (2)

Answers (2)

mukesh_s26
Explorer
0 Kudos

No , it didt work and thanks for the suggestion

Shazeb_Siraj
Explorer
0 Kudos

Hello Mukesh ,

Could you please also try to test by changing settings in Whole HU Column ?