Hi all,
We need to create PO with reference to Contract which also was created with reference to RFQ with PR reference.
Everything is okay when we cretate PO with reference to RFQ, in this case PR number is also copied to PO.
As I mentioned all documents are created with referece to each other so we need all 3 documents to be copied to PO item.
What is the origin of document Contract or PR?
# if origin of document is Contract and then you may have following
Option-1. Contract----->Create PO from Contract , here in PO you can view contract number
Option-2. Contract-----> PR----->Create PO from PR, here in PO you can view contract number and PR number
# if origin of document is PR and then you may have following
PR---> RFQ---->Contract----> PO, here in PO you can view contract number with other document numbers