Interlinking Actions VMS - IS Auto

rohit_chauhan
Contributor
0 Kudos

Hi,

I have an Interlinking action which consists of 4 elementary actions - A1, A2, A3 & A4.

The problem is sometimes one of the actions fail (e.g. A3). In such a case the vehicle is updated with A1 and A2.

My requirement is if any action fails out of A2, A3 or A4, the actions done previously should be rolled back. If action A3 fails, action A1 and A2 should be rolled back.

If any of the interlinking action fails the vehicle should come back to the state where it was before triggering the Interlinking action.

Can we do this by way of config? or is there a development which can be done.

Looking forward to your expert advices.

Best Regards,

Rohit.

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Dear Rohit,

This cannnot be through config.

This needs Development check at the end of every action .

If it is failure ,You need to perfom the Reverse actions accordingly except the complete Z actions where it does not have Alias standard actions.

Thank you,

Sudheer P.

View solution in original post

2 REPLIES 2

Former Member
0 Kudos

Dear Rohit,

This cannnot be through config.

This needs Development check at the end of every action .

If it is failure ,You need to perfom the Reverse actions accordingly except the complete Z actions where it does not have Alias standard actions.

Thank you,

Sudheer P.

Former Member
0 Kudos

Dear Rohit,

This cannnot be through config.

This needs Development check at the end of every action .

If it is failure ,You need to perfom the Reverse actions accordingly except the complete Z actions where it does not have Alias standard actions.