Hello All,

I have configured the Costing variant for sales order costing which works correctly and calculate the cost and accumulate in inEK02.

But when cost is calculated reference to the sales order then there is a difference in Material cost but activity cost are same.

I have also observed some of the components are missed in prd order..

Cost are high in sales order costing and less in production order target cost.

Plz suggest why there is the difference.. as we are using MTO scenario with variant configuration and configurable material is used...with Price indicator 'V"

Thanks...