on 07-24-2018 2:58 PM
We have a multi level configurable material which is entered in sales order.
Characteristics for the Header level VC is entered in the order;
BOM is determined using dependencies.
All characteristics for sub level VC material are inferred based on dependencies.
Two scenarios -->
I. For Multi-level VC sales order when we manually change the inferred values of sub level component before saving the order and enter header config values. Planned order not created after MRP run.
IBIN tables has only one entry.
II. For Multi-level VC sales order when we do not change the inferred values of sub level component before saving the order and only enter header config values. Planned order is created after MRP run.
IBIN tables has two entries.
ritesh.dube, request your inputs.
Regards,
KP
Hey Friend,
Sorry i was kinda inactive for a very long time. I am not sure if you still have this issue or you got any resolution. To me the first scenario sounds like inconsistency in configuration resulting in no planning. Please check out and revert.
Thanks
Ritesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
8 | |
6 | |
5 | |
5 | |
4 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.