We currently have inspection plans in place. I am trying to make some of the characteristics long term and allow the rest to be short term. In my test, I made a few MIC's long term characteristics and did not enter a value and set them as optional.
When I go into the inspection record I released and reset inspection completion(to change to LTIN), then go into results ,the long term characteristics aren't populating. It is completely blank (attached)
Here is what I did to set up long term inspection-
In the MIC, in control indicators, I have selected optional charc and long-term inspection
In the Inspection plan, also in the control indicators, I have selected optional charc so when the UD is made and there aren't any values it doesn't force them closed.
What am I missing? I tried to see if there was an inspection type needed to link the inspection plan but couldn't find any end-to-end document on utilizing long-term inspection.
Any information is helpful.