on 02-19-2024 1:39 AM
Hi,
There is plan cost/revenue can be uploaded to project.
Example:
Planned Revenue : $ 150,000 ; Planned Cost : $ 100,000
The project started with POC. However, when the project started half way, total cost was overspent. The expected cost will increase to $150,000. Project Manager plan to update the expected cost to $200,000
What is the best practice to handle this scenario? How to post provision of lost amount?
thank you.
User | Count |
---|---|
100 | |
8 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.