Automatically FU rebuilding Planning

In this blog will explain a way How To Rebuild Automatically FU Planning if a Freight Document is cancelled.

Let’s say you Cancel you Freight Document which was Automatically Planning explain in the last Blog.( Automatic Freight Unit Planning | SAP Blogs)

Now you need to replan it also automatically, follow these steps:

Create a New strategy for the TOR_CHACO:

1

1

Assign Methods to a Strategy ( you can try to use REBUILDFUH -Rebuilds all freight units or REBUILD_FU-  Rebuilds unplanned, unfixed FUs )

Created an BRF+ for the /SCMTMS/CC_TOR_STRAT ( Make sure you condition use some parameters which is change on the Demand document (SO/PO/ OD /IBD) like Shipping Condition is change to call the Rebuild Planning).

 

Assign the BRF+ in the FU Doc Type.

 

In order to Cancel the FO and remove the FU from the Planning use the Strategy (TOR_REM_PL)

Created a Condition in /SCMTMS/CC_TOR_STRAT define a BRF+

 

Assigned the Condition in the FO document type.

With these steps if you Cancel you Freight Order will be recall the Freight Unit creation delete that and create a new for retrigger the Automatically Planning mentioned in the previous Blog.

Thanks all.

Rogerio Lima.

 

Assigned Tags

      4 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Rene Criellaard
      Rene Criellaard

      Hi Rogerio,

      thanks for your detailed explained blog. I have created the automatic FU planning in S4-2022 FP1 with Sales Order based FU creation and that works fine. But the rebuilding isn't working fine. After deletion of the Freight Order the Freight Unit remains unplanned.

      Tested the same scenario in an older version based on a FWO and it's working as per expectation.

      Do you know if there are limitations for this rebuilding set-up ?

      Author's profile photo Rogerio Lima
      Rogerio Lima
      Blog Post Author

      Hi Rene,

      I updated the Blog with some more information which can be useful for the rebuild

      Regards

      Rogerio

      Author's profile photo Carlos Garrido
      Carlos Garrido

      Hola,

      Al crear la estrategia, ¿qué servicio le asignaste?

      Por otro lado, cuando estoy intentando asignar el método TOR_REM_PL a mi estrategia no me deja.

      Author's profile photo Rogerio Lima
      Rogerio Lima
      Blog Post Author

      Hola,

      Es necesario asignar la estrategia  ZCANCEL  al servicio TOR_CHACO en (Define Strategy Customizing)..