Personal Insights
Adjustment Period for Planned Independent Requirements
Business Requirement: The Planned Independent requirement should not be considered in a short-term horizon. Let’s say the planner enters PIR’s for the current month and the following month. The sales orders arrive which consumes the PIR’s. This means the remaining Planned Independent Requirements should not be considered for production.
Solution: You may use the function called ‘Adjustment Period’ in the MRP Group. You must define the period of adjustment for PIR’s as 22 days as an example. The adjustment period is calculated in workdays (according to the Factory calendar) therefore 22 workdays would mean an adjustment period of 1 calendar month. Also, the indicator for Adjustment of Planned Independent Requirements must be assigned. This indicator is used to identify if the adjustment is performed backwards or forwards. You can also determine if the adjustment of PIR’s is valid for all planning strategies or only for PIR’s that are planned with a strategy which includes the consumption of customer and independent requirements.
Now, lets create Planned Independent Requirements for a material. Currently the MRP group with adjustment period is not assigned to the material. You can see that PIR’s are displayed as a demand in MD04.
Now, assign the MRP group ‘0001’ with adjustment period to the material and then run MD04 again.
You can see the PIR’s are displayed in MD04 however not considered for planning. The field ‘Available Quantity’ for each PIR is blank.
Conclusion: Adjustment period can be used to ignore Planned Independent Requirements from planning run.
Click on the below link to buy “Handbook for SAP PP in S/4HANA: Production Planning and Execution in SAP S/4HANA” by Himanshu Goel.
https://link.springer.com/book/10.1007/978-1-4842-8566-4
About this Book:
If you’re looking to increase your knowledge of one of the core modules of SAP S/4HANA, this is the book for you. Settle in and let a long-time SAP professional guide you through the SAP Production Planning and Execution module.
Author Himanshu Goel begins by explaining the nuts and bolts of production planning in SAP S/4HANA, before delving into various manufacturing methodologies such as discrete manufacturing, repetitive manufacturing, and process industry. He’ll then walk you through setting up master data such as the material master, bill of material, work center, routing, and production version. You’ll then learn, step-by-step, how SAP PP processes are established from production order-based manufacturing to process order-based manufacturing.
This book explains the complex concepts of production planning and execution in a straightforward manner and makes for an invaluable guide for SAP PP users from production planners to shop floor managers and even junior/mid-level SAP PP consultants. After reading this book, you’ll fully understand the concepts of SAP PP, and have insight into the latest developments in S/4HANA.
The concept explained nicely and concisely!
You might want to turn the text "https://link.springer.com/book/10.1007/978-1-4842-8566-4#about-this-book" into an actual clickable hyperlink.
Dominik Tylczynski Thanks for the suggestion. Activated the link