How to Control the Excess/Additional Goods Issue of Components to Process Order

Business Scenario:
During the Confirmation of the Process Order, which is activated with Backflush (Auto GI, during the confirmation), System is not allowing the Additional Good issues/increase the Component Quantity manually. Getting the Error message, when saving the Confirmation.

Execution Steps as follws below
Create the Process Order using the T Code: COR1
In this Process Order, Components are activated with Backflush Indicator, which will enable automatic goods issue during the confirmation. The Component Quantities are 5 L for each of the component

Release the Process Order using theT Code: COR2

This order is in the Released & saved in the change mode.
Confirm the Process Order using the T Code: COR6N

During the confirmation, User is trying to add the additional goods issue (or) increasing the Component Quantity manually.
In the Goods movement tab>>Increasing the component Qty from 5 to 10 (more than 5)

 After manually Increasing Component Quantity, then Click on Save >> Getting the below Screen

If we look at the Error details
System tis throwing the Error, for this additional Goods Issue, changed manually

Root cause of this Error
Look at the System Message control stetting in the Configuration using  T Code: OMCQ

Solution Proposed:
If we change Error message to Warning message, (E to W) System will allow the Additional (or) Excess Goods issue of the Component Quantities manually, during the Confirmation.

Hope, this is of some Useful Info. Kindly update with your  Valuable Feedback/Comments/Inputs.
Thanks & Regards
Raja Sekhara Reddy Bannuru

Assigned Tags

      7 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Anil Kumar
      Anil Kumar

      Good Information sir... Tq...

      Author's profile photo RAJA SEKHARA REDDY BANNURU
      RAJA SEKHARA REDDY BANNURU
      Blog Post Author

      Thanks Anil, for the Kind Feeback

      Author's profile photo SUNIL PATIL
      SUNIL PATIL

      Thanks Raja for real time scenario creation and nice explanation.

      System will allow if we change E to W message, but does it suite for SAP standard practice?

      Please keep posting for such messages.

      Best Regrads

      Sunil Patil

      Author's profile photo RAJA SEKHARA REDDY BANNURU
      RAJA SEKHARA REDDY BANNURU
      Blog Post Author

      Hi Sunil,

      Thanks A Lot, for sharing the Kind Feedback.
      Yes, System will allow the all the possible three Options , Error (or) Warning (or) No Message.
      This is can be Set according to the Business Requirements.

      Best Regards : Raja

      Author's profile photo Hariteja Bandla
      Hariteja Bandla

      Hi Raja Sir,

      Thank you soo much for detailed explanation with real time scenario

      Thanks,

      Hariteja Bandla

      Author's profile photo RAJA SEKHARA REDDY BANNURU
      RAJA SEKHARA REDDY BANNURU
      Blog Post Author

      Hi Hari,

      Thanks A Lot, for the Kind Feedback.

      Best Regards : Raja

      Author's profile photo Carolina Perroglio
      Carolina Perroglio

      Hey Raja, thanks for sharing...
      Another situation that I am facing, see if you can help me:

      After release production order the system reserved a quantity that is available in stock, but when we change the quantity in COR2 the system is allowing ecxessive reservation quantity.

      Is there any way to avoid that?