Author's profile photo Arsalan Aslam

Cost Center and Cost Element wise Variable and Fixed Planning

Background:

The blog is prepared for clarifying how system provides Fixed and Variable costs breakup from report. There are a lot of times client asks to define additional activities to distribute Variable and Fixed nature costs.

This breakup is available from SAP standard functionality and does not necessitate additional activity.

In below example a single activity of Setup Cost is taken for example where both Plan Fixed/ Variable and Actual Fixed/Variable rate calculation is explained. Kindly ignore GLs description as these description might not be realistic.

System breaks down Fixed and Variable based on Plan entered GL and Cost Center wise as shown below. This blog is divided into two portions Plan Fixed and Variable Price Calculation and Actual Fixed and Variable Price Calculation

 

Plan Fixed and Variable Price Calculation:

Entered%20Plan%20in%20Variable%20and%20Fixed%20Portions

Entered Plan in Variable and Fixed Portions

Referring%20Entered%20Plan

Referring Entered Plan

 

We have also mentioned Plan Activity and Capacity against the same Activity.

Plan%20Activity%20and%20Capacity%20Maintained

Plan Activity and Capacity Maintained

Now both the above costs will be segregated based on formula where Fixed Costs are divided with Plan Capacity and Variable Costs are divided by Plan Activity in order to calculate Plan Fixed and Plan Variable Prices. Breakup is prepared below for reference:

GL Heads Plan Fixed Plan Variable Plan Capacity Plan Activity
Entertainment Expense 250,000 10000
Setup Fixed Cost 100,000 10000
Setup Variable Cost 50,000 10000
Total 350,000 50,000

 

Fixed Price Rate              = (250000+100000)/10000

= 35

 

Variable Price Rate          = (50000)/10000

= 5

 

Total Plan Price               = 40

 

**In the above manner, we can obtain both Variable and Fixed Plan Rate as calculated by system shown below.

Plan%20Price%20Calculated

Plan Price Calculated

Until now we have Plan Prices calculated, moving forward system will calculate Actual Prices based on below basis.

 

Actual Fixed and Variable Price Calculation:

There are some actual postings made in system in order to allow the system to calculate actual prices.

Actual%20Postings

Actual Postings

Firstly, system will deduct all the Actual Fixed Costs posted in GLs which were planned to remain fixed. This cost equals to 400,000/=

Accordingly, Fixed rate will be calculated by dividing the 400,000 total with Actual Activity.

GL Heads Actual Fixed Actual Variable Actual Activity
Entertainment Expense 250,000
Setup Fixed Cost 150,000
Setup Variable Cost 60,000 2,457.437
Total 400,000 60,000

 

Fixed Cost           = (250000 + 150000) / 2,457.437

= 162.771

 

**Variable cost will be calculated as Total Cost minus Fixed Cost divided by Actual Activity

 

Variable Cost     = (460000 – 400000) / 2,457.437

= 24.415

 

Total Cost           = 187.186

 

**System taken Price Unit as 10, therefore multiplying above amount with 10 will match the above rates with system calculations.

Actual%20Price%20Calculated

Actual Price Calculated

 

Conclusion:

Concluding the blog it can be said that segregating the costs into Variable and Fixed nature will no longer require any additional activity. It can be covered with SAP Standard Feature of Fixed and Variable Price Calculation using KSPI and KSII.

Assigned Tags

      3 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Naveenthar Chandrasekaran
      Naveenthar Chandrasekaran

      Hi Arslan,

       

      Well explained, also, can you please mention the t-code which you used in these example including input t-codes and report t-codes?

       

      Regards

      Naveen

      Author's profile photo Arsalan Aslam
      Arsalan Aslam
      Blog Post Author

      KSS4 - Plan Cost Splitting

      KSPI - Plan Price Calculation

      KSS2 - Actual Cost Splitting

      KSII - Actual Price Calculation

      KP06 - Cost Center Planning

      KP26 - Activity Planning

      S_ALR_7013611 - Cost Center Plan vs Actual Postings Report

      Author's profile photo Kathiresan Nagarajan
      Kathiresan Nagarajan

      Hi Arsalan,

       

      Thanks for bringing up this topic and sharing it across.

      I've noticed a line - "Now both the above costs will be segregated based on formula where Fixed Costs are divided with Plan Capacity and Variable Costs are divided by Plan Activity in order to calculate Plan Fixed and Plan Variable Prices."

      In the activity type master data, there is a field called Price indicator which will indicate the system to compute the rates based on activity quantity or capacity. For a single activity type, calculation will be based on either quantity or capacity, not both. Irrespective whether the cost is fixed or variable, rate will be determined based on only quantity or only capacity.

       

      Thanks,

      Kathir