Guide to Blanket Purchase Orders

Introduction

In the case of procurement we usually come across scenarios where we are procuring goods/services of low value/importance and this action maybe repeated over a period of time, in this case we make use of Blanket Purchase Orders.

Let me help you with an example, purchase of Maintenance/Office Utility materials/stationery are procured time and again, here we can limit the posting of GR/SES.

Why Blanket Purchase Order ?

1)Blanket PO nullifies the need of Material Master/Service Master/Goods Receipt or Service Entry Sheet posting and it we can make direct invoice posting.

2)As a user, there is provision to maintain a validity period in the Purchase Order.

3)Additionally, we can maintain a “Limit” to put a cap on the total spending.

4)If the validity period expires or the limit is extended, “Invoice will be blocked for Payment” .

How To Work With Blanket Purchase Order ?

1)Create a Purchase Order of type “FO-Framework Order”, Account Assignment Category as “K-Cost Center”, Item category as “B-Limits”.

In case of Limits, the Expected Value is similar to Net Price and Overall Limit is the maximum amount of Invoicing to be allowed for this material/service.

Additionally, we can also maintain Validity Period in the header.

2) Post an Invoice(MIRO)

Here an error message is thrown as the Invoice value exceeds overall limit as amount is greater than the overall limit specified in Purchase Order(Tolerance limits might also comes into the picture).

If we go ahead and try to post the same, it will be blocked for Payment.

Similar action will come into force if the Invoice Date is outside the validity period.

Conclusion

Creation of a new purchase order frequently for procurement of goods of less importance and taking delivery against the order on a recurring basis is frequently considered uneconomical and time consuming, Blanket Orders are here to our rescue.

Now that we have a brief overview of the practice and use of Blanket Orders, we can suggest the same for our business processes as and when required.

 

 

 

Assigned Tags

      11 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Prashun Shetty
      Prashun Shetty

      Good one Salman.

      keep adding value to others life.

      if you would have added few info about GL account , how to add or whether it will pick automatically.

      Author's profile photo Syed Salman
      Syed Salman
      Blog Post Author

      Thanks Prashun !

      Great Point, Noted 🙂

      Author's profile photo S Abinath
      S Abinath

      Hi,

      Clear explanation... hope this will help a lot for many

      Author's profile photo Syed Salman
      Syed Salman
      Blog Post Author

      🙂

      Author's profile photo Bhumika dodia
      Bhumika dodia

      Hi ,

      Nice explanation , where we can avoid long cycle of GRN/SES by just paying inoicve bills.

       

      Author's profile photo Avinash Kumar
      Avinash Kumar

      Well explained.

      Author's profile photo Martin Plewnia
      Martin Plewnia

      Hallo Salman,

      thanks a lot for this introduction.

      I have a question: How does this apply to SAP S4 Hana?

      Is the item type B also supported by the new Fiori apps (didn't work for me yet)

      or do we have 2 separate, incompatible roads now:

      1. ECC or S4 SAP GUI with item type B  (described by you)
      2. S/4 Hana Fiori with with new item type E ("extended limit" ).

      I would be grateful  for some comments or reading advice.

       

      Regards

      Martin Plewnia
      Berlin

       

       

      Author's profile photo Arturo Arnaiz
      Arturo Arnaiz

      Hello Martin,

       

      On S/4 Hana 1909 you can create a Framework Order in two ways:

      1. Via the Create Purchase Order App, where you will set the item as "B" Limit, then expand and enter the relevant information for the blanket PO.
      2. Via the Manage Purchase Order App, where you will create a limit item and then on the schedule line with tab you define the validity period, when you save system will create a Blanket PO with item category "E".

       

      Please give it a try and revert,

      Thanks

       

       

      Author's profile photo Leopold Straubinger
      Leopold Straubinger

      Hi Syed Salman ,

      my question goes into the same direction as the one of Martin Plewnia:

      How does the Fiori approach to Limit Orders differ from the ECC approach?

      Some points already mentioned:

      • Different item category (B & E)
      • Validity period (are validity dates still a thing in Fiori?)
      • Differentiation between Service and Material in Fiori (Product Type Group) possible

      Do you (or someone else) have an idea on how SAP will go forward with this feature in the future?

       

      Best regards

      Leopold

      Author's profile photo sudhagar Vijayakumar
      sudhagar Vijayakumar

      Nice note and Very well explained. Thanks to Salman

      Author's profile photo Nagy Hamed
      Nagy Hamed

      Thanks, Syed.

      but, if the Validity date of this PO (Framework) in the past Invoice can be done no issue for that.

      Only the Invoice will be blocked in case the value is exceeded the overall value,

       

      BR,