HI Folks,

This Blogs is to make aware of the functionality that SAP has provided. Lets consider a business scenario where the business user may accidently close a task that is assigned to them. So the user were not able to reset the task status back to release from complete or from successful status. So the user used to create a new Task and perform the corrections again.

 

SAP has provided Notes to achieve this functionality

2829742 – Pre-requisite for the below note-

2840136 – Note to implement the required functionality.

 

After implementing the above notes, enable the functionality of resetting by setting the flag as active, as shown in the below image

Problem notification Analysis ( Reset task to be released ) – X

This flag will be enabled only after implementing the note.

 

After enabling the flag, the button shown in the below screenshot will be available and it can be used to reset the task status back to release from completed.

 

Many new functionality have been added by the SAP, but we are not aware of these notes. Hope this blogs save the development .

 

 

 

Assigned Tags

      2 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Vignesh Veerasamy
      Vignesh Veerasamy

      Hi Abhishek Parab

      Very useful document.

      One point : though both the notes are mentioned as applicable for S4CORE 102 components not shown in SNOTE browser.

      Vignesh V

      Author's profile photo Abhishek Parab
      Abhishek Parab
      Blog Post Author

      Try downloading the Notes using the S-user id and then upload the same( .SAR file) using upload option  present in the Snote option. then i guess you will be able to see the same. There are a couple of manual steps as well you need to perform in-order to activate this functionality

       

       

      Thanks and Regards,