Skip to Content
Product Information
Author's profile photo Ann Hustis

Do you need the DDMRP functionality offered in S/4HANA?

I love SAP. But I’m having a hard time understanding the excitement for Demand Driven MRP (DDMRP) functionality that SAP first offered in its S/4HANA 1709 version. I’ve studied DDMRP and have had many discussions with colleagues.  We cannot see how DDMRP solves planning problems that weren’t already solved with classic MRP functionality we’ve had since the R/3 days!  DDMRP requires the use of Fiori apps; additional master data; and a new way of doing exception monitoring so the functionality requires a lot more know-how. In my 10 years of SAP PP optimization consulting I have never seen a client use even classic MRP functionality correctly!  Why throw additional functionality at them?

Manufacturing companies are in business to make and deliver products on-time and at a profit to customers.  They are not in the business of keeping up with the latest SAP offering.

In this blog I’ll discuss how DDMRP solves various planning problems and how classic SAP has solved the same problems since its early days.  I assume the reader already knows how DDMRP works.  If not, please watch this excellent YouTube video by Caetano Almeida who is a Support Architect at SAP.  Please start watching at 21:41 when Caetano begins talking about S/4HANA 1709.  https://www.youtube.com/watch?v=g2JmSkuUAxw

I will refer to the product structures below.  LT = lead time

ROH1 would be a good candidate for DDMRP because it has a long lead time and consistent usage.

Two%20product%20structures

Two product structures

 

Here is a summary of the planning problems solved by DDMRP and an equivalent solution that has been in SAP since the R/3 days.

Planning Problem Solutions that have been in SAP since R/3 Solution using DDMRP in S/4HANA starting at release 1709
The “forecast is always wrong” leading to high inventory of some components. Use the correct planning strategy Use DDMRP MRP type D1 to decouple the components’ plan from the finished goods forecast.
Want to reduce noise in the planning of low-level components. For PD planned materials use safety stock that is partially relevant to MRP
Want to shorten the critical path

Use consumption-based planning for some low-level components (detailed below).

Or use Kanban planning with an MRP signal at any BOM level (not detailed below).

 

Below are detailed explanations for each point.

“The Forecast is always wrong”

One of the things that DDMRP promises to fix is the cumulative error on the planned quantity of lower level components. This is often described as the bullwhip effect.  If FERT1 and FERT2 are planned with Strategy 40 Planning with Final Assembly you will likely hold too much inventory of ROH1 a component common to both structures. This is because strategy 40 plans demand as the higher of the VSF forecast or the sales orders.

If you forecast 100 PC of FERT1 and 50 PC of FERT2 but have sales orders of 130 PC and 10 PC respectively you will plan 180 PC of FERT (130 PC + 50 PC).  If ROH1 is used 1:1 with FERT you will plan 180 PC of ROH1.  But you need only 140 PC of ROH1 for upcoming sales.

The DDMRP solution will use MRP type D1 on ROH1 and plan it independently; “decoupling it” from the forecast on the FERTs.  You will maintain inventory of ROH1 based on its average daily usage keeping the dynamic buffer quantity satisfied.

The classic SAP solution is to use a more fitting planning strategy.   So many clients don’t use any make-to-stock planning strategies other than Strategy 40.  What a shame!

If you need to plan capacity at your FERT work centers then Strategy 63 Planning with a Planning Material is more suitable for the product structures above.  You will plan 150 PCs of the “FERT family”; this is known as a Planning material.  See process flow screen shot below from the Demand Management PP-MP-DEM document found here in the SAP Library:

https://help.sap.com/erp_hcm_ias2_2015_02/helpdata/en/29/24bf53d25ab64ce10000000a174cb4/frameset.htm

 

Process%20Flow%20for%20Planning%20Strategy%2063

Process Flow for Planning Strategy 63

 

To choose the correct planning strategy you will answer these two questions:

  1. With which quantities will you forecast: individual FERTs or the family of FERTs?
  2. Where will you stock the assembly prior to the receipt of the sales order: the FERTs, the HALBs or the ROHs?  See Stock keeping at different BOM levels diagram below.

Stock%20keeping%20at%20different%20BOM%20levels

Stock keeping at different BOM levels

Let’s assume you’ve offered your customer a 10-day lead time.

Using correct master data settings, you will stock only HALB1 based on the forecast for the FERT family because it and its ROHs have long lead times.  MRP will plan 150 PCs of HALB1 because you’ve forecasted 150 PCs of the “FERT family”. If you sell 130 PC of FERT1 and 10 PC of FERT2 you will have only 10 extra PCs of HALB1 and nothing extra of the other HALBs and ROHs.  Therefore, you hold lower overall inventory compared to Strategy 40.

HALB2, HALB3, ROH3 and ROH4 will be planned once the sales orders for FERT1 and FERT2 are entered.  This is not a problem because with a 10-day lead time you can purchase ROH3 and ROH4 and make HALB2 and HALB3 in time.

Or, if you do not need to plan capacity at your FERT work centers because capacity is always available then consider using planning Strategy 70 Planning for Sub Assembly instead.  Enter 150 PCs of VSFB forecast for HALB1.  MRP will drive you to stock HALB1 prior to the receipt of the sales orders for FERT1 and FERT2.  Once the sales orders are entered you will procure ROH3, ROH4, HALB2 and HALB3.  Again, you have time because your promised lead time to customer is 10 days.  Here is a link to planning strategy 70 in the Demand Management PP-MP-DEM document found in the SAP Library:

https://help.sap.com/erp_hcm_ias2_2015_02/helpdata/en/29/24bf53d25ab64ce10000000a174cb4/frameset.htm

Choose a planning strategy that allows you to stock at the cheapest/most flexible BOM level while still meeting the promised lead time to customer

 

Reduce noise (exception messages) on lower level components

Another thing that DDMRP promises to fix is the high volume of exception messages you get on ROH1 when the quantity or date of the demand for FERT1 and FERT2 changes.  This is because by using the DDMRP type D1 on ROH1 you decouple its planning from the BOM structures above it.

With classic MRP Plan on Demand (MRP type PD) when you increase the quantity of the FERT demand or move it to a sooner date, the scheduled supply element such as a purchase order for ROH1 is hit with exception message 10 which tells the planner to “expedite supply”.

But classic SAP already has a solution to this problem.  Again, unfortunately, not used by most clients!

Make Safety Stock partially relevant to MRP

Within configuration you can make safety stock partially relevant to MRP.  So, for example, if you configure safety stock 60% relevant to MRP it means that you can dip up to 60% into safety stock without causing MRP to create a procurement element, or hit a scheduled receipt with exception message 10.  Here is the configuration setting within MRP Group:

OPPR%20Carry%20Out%20Overall%20Maintenance%20of%20MRP%20Groups

OPPR Carry Out Overall Maintenance of MRP Groups

Let’s say you plan ROH1 with MRP type PD and you’ve set a safety stock level of 110 PC.  Consider this situation for the Stock Requirements List if safety stock is not partially relevant to MRP (the SAP delivered setting).  See the screen shot below.

Stock%20Requirements%20List

Stock Requirements List with standard behavior of safety stock

Two purchase requisitions were created, one to satisfy safety stock and the second to satisfy the dependent requirement.  Exception Message 30 tells the planner to convert to a purchase order immediately and expedite.   Exception Message 96 tells the planner the stock has fallen below the safety stock level.

Once you configure safety stock to be 60% relevant to MRP you can partially dip into safety stock without MRP creating a purchase requisition.  See screen shot below.

Stock%20Req.%20List%20with%20SS%2060%25%20relevant%20to%20MRP

Stock Requirements List with safety stock configured to be 60% relevant to MRP

Consider this Slug material to be ROH1 in our product structure.  The demand for the FERTs can increase slightly or be scheduled to a sooner date without causing MRP to create a purchase requisition.  When the safety stock level is eventually breached by demand that exceeds 60% of 110 PC a single purchase requisition will be planned to satisfy both the dependent requirement and to bring the safety stock level back up to 110 PC.

Shorten the critical path

Use consumption-based planning

Just like planning strategy 40 doesn’t suit all make to stock demand planning, MRP type PD doesn’t suit all supply planning.  Consider using consumption-based planning on materials where it makes sense.  Usually these will be at the lowest level of the BOM structure, the ROH materials.  In the table below we can see a general rule of thumb where each MRP type might be used.

Table%20of%20MRP%20Type%20usage%3A

Table of MRP Type usage:

 

There are two main types of consumption-based planning:

  1. Reorder point planning – good for short lead time components
  2. Consumption forecasting – good for long lead time components that have predicable usage; they are widely used meaning that they occur in several BOMs.

When component materials are planned using either form of consumption-based planning the demand signal is cut off as seen in the revised product structure below.  The three ROH materials are planned in their own little worlds.

Product%20Structure%20with%20Consumption%20Planned%20ROHs

Product Structure with Consumption Planned ROHs

 

The critical path also known as the total replenishment lead time to make FERT1 is now only 22 days (2 + 20) since all ROH materials are planned by consumption-based planning; they are considered to always be in stock.  If all materials were planned with MRP type PD instead, the critical path would be 57 days (2 + 20 + 35).

  • MRP Type V1 requires the planner to set a reorder point in the material master such that once it is breached you will not run out of inventory before the new supply arrives. For this the planner must consider the lead time of the material and the expected usage during the lead time.  You can find the expected usage from SAP report MC42 Range of Coverage based on Usage.
  • MRP Type VV requires a material forecast (demand) to be generated (usually based on historical consumption using a model such as seasonal, trend, seasonal-trend, constant, etc.). MRP runs to provide planned supply elements to satisfy the material’s forecast. Dynamic safety stock also known as range of coverage profile is often used with VV planning to cover spikes in demand.

Another added benefit of consumption-based planning is that it forgives capacity overloads.  If the FERT and/or HALB work centers are overloaded you will not carry excess inventory of ROH materials.

Summary

Supply chains are all different, hence planning problems are diverse.  To address this, SAP has offered a large toolbox of planning functionality since the R/3 days. Clients choose the best solutions for their needs.  As consultants we should encourage them to exhaust classic solutions first before introducing new functionality such as DDMRP because it is not cheap. It requires the use of Fiori apps, additional master data and additional processing know-how.

I won’t offer a glass of water to a drowning man!

Assigned Tags

      37 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Dominik Tylczynski
      Dominik Tylczynski

      That is a great piece of writing. I especially appreciate you showing how classic SAP MRP addresses challenges in supply chain planning, the challenges that supposedly only DDMRP is able to solve.

      Looks like classic MRP is such a powerful tool. We just need to use it correctly and explore it's various features.

      Dominik Tylczynski

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Thank you Dominik.  And thank you again for peer-reviewing it.  You've been my mentor for several years.

      Author's profile photo Dominik Tylczynski
      Dominik Tylczynski

      Likewise, I've learned a lot from you and still do!

      Author's profile photo R Brahmankar
      R Brahmankar

      Hello Anne,

      Indeed a nice and very useful piece.

      Manufacturing companies are in business to make and deliver products on-time and at a profit to customers.  They are not in the business of keeping up with the latest SAP offering

      On this point, I couldn't agree more

      And planning strategy 63 planning with a Planning Material is good when forecast is capacity.

      This strategy is often used to manage a simple but effective method of capacity planning.

      For planning of dependent materials where you have a long lead time you can define dummy BOM for planning material with critical assembly and raw materials.

      As you will have the forecast on planning material and MRP will create procurement and production of  critical assembly and raw materials as per planning material BOM.

      When actual sales orders come for finished goods which can use it and plan also short lead time products which is not a part of planning material BOM.

      However if your capacities for finished goods production lines are always full then you have no need of planning material BOM you can directly use finished goods for planning.

      Only disadvantages of planning strategy 63 is that ATP check is against the forecast (PIR) without supply elements.

      Best Regards,

      R.Brahmankar

       

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Thanks for your comment Rupesh.

      When you say, “Only disadvantage of planning strategy 63 is that ATP check is against the forecast (PIR) without supply elements”, I don’t see that as a big disadvantage; it just requires careful planning.

      If the production planner ensures that he has capacity for all planned orders within the capacity planning period (CM01 for let’s say the next 9 weeks) and the material planners are driving purchases to be receipted in-time by closely monitoring their exception messages and traffic lights (MD06/MD07) then the ATP check against the forecast will be robust.

      If either the production planners or the material planners spot a problem in week 7, 8 or 9 they must deal with it now by:  adding production capacity; subcontracting some production; purchasing from an alternate vendor; or as a last resort reducing the forecast before a sales order is promised against it.

      Thanks again for your comment.  I appreciate it!

       

      Author's profile photo R Brahmankar
      R Brahmankar

      Hello Anne,

      What you said is right,  however when I talk about planning I considered SD, PP and MM. So when sales orders come for finished goods it consumes a forecast of planning material and which performs the ATP check it will be against the PIR of planning material.

      During an ATP check against planning, you can only carry out the confirmation against unused planned independent requirements and not against stock or inward movement.

      Now consider the scenario if you have a scheduling agreement where all schedule lines perform the ATP check and consume the forecast and if the new sales order comes with the earliest requirement will remain unconfirmed in this case. So in that case we need to confirm against replenishment lead time with a fixed date and quantity which does not represent the real capacity situation.

      In the sales order, the availability check is carried out with planned independent requirements for the planning material. For this, the sales orders for all materials that are consumed against the same planning material which also lead to performance and consumption issues if you have large sales volume and high number of FG material assignment to planning material.

      For frequently asked questions and problems in this area please have a look on SAP note.
      622299 – Consulting: Availability check against planning

      Apart from these limitations as per my experience with strategy 63  it is one of the best suitable planning strategies.

      Best Regards,

      R.Brahmankar

      Author's profile photo Dhia djebbi
      Dhia djebbi

      Hello everyone, i AM  working on DDMRP and

      i have an issue  in showing PIR in the figure of "Goods Issue / PIR Quantity"  in manage

      buffer levels ( Fiori) despite that i  create it with "MD61" and  it appears in Stock requirements/List

      "MD04",

      Best Regards,

      DJEBBI.

      Author's profile photo Pulla Rao Tulava
      Pulla Rao Tulava

      Interesting, very good insights, thanks for sharing..?

      Author's profile photo Sharat Sugur
      Sharat Sugur

      Hello Ann,

      Very rich content and thought. Nice blog and unlocking many questions. Thank you for sharing.

      Author's profile photo Raj Krish
      Raj Krish

      Ann,  interesting article indeed...   We tend to think new solutions are way better than the existing ones, but your article describes classic MRP has way more functionality than the new DDMRP.  thanks for sharing

      Author's profile photo Juan Pablo Blanco Zerlín
      Juan Pablo Blanco Zerlín

      One of the best post I've ever read. Thanks for the explanation Ann!

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Whoa!  So nice.  Thank you Juan!

      Author's profile photo Pradeep Kumar
      Pradeep Kumar

      Hello Ann.

      First of all thanks for sharing wonderful blog  comparing classic MRP and Advanced DDMRP, and  point out general  Planning problems.

      I agree, still classic MRP has powerful  planning procedure , when it is used effectively,and

      customer  should be matured enough in  classic MRP before  implementing  DDMRP.

      Thanks for discussing about planning strategy  planning  with plan.Mat 63, it is very good planning strategy to plan capacity  and common / non variable parts ,but pre assumption is stock level for variable parts should be taken care, other wise customer delivery date can be met, since Regular sales ATP check is not performed  considering stock and inward receipts.

      Author's profile photo Mike Murray
      Mike Murray

      This is excellent work.  I am currently an IT Director, but a former MM/PP consultant, and am constantly battling the business on why they need to use the "latest and greatest" when I am certain they don't even use what they have properly.  One more piece of information in my toolkit.

      Thanks!

      Author's profile photo Martin Preiss
      Martin Preiss

      Excellent article. All of it. And especially the part about 'Make safety stock partially available'. This function indeed should be used much much more often.

      Author's profile photo Rizky Octavianto
      Rizky Octavianto

      Hi Ann,

      I have a problem understanding this part:

      ‘If you forecast 100 PC of FERT1 and 50 PC of FERT2 but have sales orders of 130 PC and 10 PC respectively you will plan 180 PC of FERT (130 PC + 50 PC).  If ROH1 is used 1:1 with FERT you will plan 180 PC of ROH1.  But you need only 140 PC of ROH1 for upcoming sales.’

      Can you please explain? why is the planning output for FERT 180 PC instead of 150?

      Thank you in advance

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Hi Rizky,

      Thank you for your question.

      When you plan independent requirements (PIRs) with Planning Strategy 40 Planning with Final Assembly, MRP will plan supply to the HIGHER of the PIRs or the sales orders, within the consumption period set on the Material Master.

      In my example above the requirements for FERT1 is 130 PC because the sales order is higher than the PIRs of 100 PC.  The requirement for FERT2 is 50 PC from the PIRs because it is higher than the sales orders of 10 PC.  So the sum of these requirements is 180 PC.

      Here is a link to SAP Help on Planning Strategy 40: https://help.sap.com/viewer/74c0b3a391174482a66a3a23bb28c10d/6.17.14/en-US/3923bf53d25ab64ce10000000a174cb4.html

      Please look at paragraph 5: Requirements from the sales orders are passed on to production and can lead to changes made to procurement if the requirements from the sales orders exceed the planned independent requirement quantities. If there is insufficient coverage of components (the sales order quantities exceed the planned independent requirement quantities), the sales orders cannot be confirmed. The system therefore automatically adjusts the master plan.

      The reason that Strategy 40 is used so widely is that it is flexible.  If your forecast is too low the sales orders will add to the plan.

      Contrast this to Planning Strategy 10 Net Requirements Planning where the requirements are only the PIRs.  The sales orders are shown on the Stock Requirements List as information only; they do not influence the demand.

      I have a fantastic PDF document written by SAP called Demand Management (PP-MP-DEM) that explains in detail (all 214 pages) all of the planning strategies.  Please let me know if you'd like me to email you a copy.

      I hope this helps.  Please feel free to ask any follow up questions.

       

       

       

      Author's profile photo Rizky Octavianto
      Rizky Octavianto

      Hi Ann,

      Thank you so much for the explanation, it's really enlightening. I've been in two SAP PP implementation and I have not yet learned anything about planning because it's often overlooked here in Indonesia and I would love to be able to change this one day if I can progress as a consultant.

      Please do share me the document (PP-MP-DEM) if you would mind, my email is rizky.octavianto@eclectic.co.id. Would love to dig deeper into this part of SAP PP.

      Thank you again, this is a really great article. Hope you'll have a good day.

       

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Perfect.  I just sent it to you!

      Author's profile photo Shanmugam Sathiyamurthy
      Shanmugam Sathiyamurthy

      Excellent and comprehensive document to show how Demand Driven Planning can be implemented with traditional MRP itself. I love this document.

      Incidentally, I suggested solution almost in this line (other than using strategy 50 instead of 63) and all down the level BoM with approach explained here.

      As expressed here, many features in standard MRP line strategies 50,63, 70,  Reorder Planning, Schedule Margin Key, Planning Horizon, Maximum stock level, Safety stock availability, automatic reorder point calculations, availability check parameters, standard missing parts reports CO24, are not being utilised by many users. I explain the feature of all these parameters to my client and they are excited to use them and started to realise the benefits.

      If you don't mind can you share the document on Demand Management (PP-MP-DEM) and my email address is ssathiyamurthy@yahoo.co.in 

       

       

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Thanks for your comment Shanmugam.

      I emailed you the document.

      All the best.

      Author's profile photo Rohit Nagdeve
      Rohit Nagdeve

      Dear Mam,

      Great article.

      Thanks a lot for sharing.

      Please mail me the document (PP-MP-DEM)

      rohitnagdeve@yahoo.com

      Kindly consider.

      Thanks in advance.

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Thank you Rohit!

      I just emailed the document to you.

       

      Author's profile photo Rohit Nagdeve
      Rohit Nagdeve

      Dear Mam,

      Received the document.

      Thanks a lot.

      Author's profile photo Puneet Puri
      Puneet Puri

      Hi Ann

      Thanks for sharing ground level reality .Even we are also using 10/20 for FERT & 70 for HALB and share safety stock for ROH  with one enhancement to Enable MSL functionality in demand based planning. But still believe that these  are some ground level challenges and SAP has provided various Exits,Badi & Config to resolve it as per industry practice.

      BR

      Author's profile photo Arturo García Díez
      Arturo García Díez

      Hi Ann, excellent article. Thanks for sharing your knoweledge.

      I'm interested on the document PP-MP-DEM Could you shared with me the document (arturogarciadiez@hotmail.com)

       

      Thanks in advance.

       

      Arturo.

       

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Hello Arturo,

      I emailed it to you just now.

      Regards,

      Ann

       

      Author's profile photo Qian Yu Gao
      Qian Yu Gao

      Dear Mam,

      Great article.

      Thanks a lot for sharing.

      Please mail me the document (PP-MP-DEM)

      teresa1216.hsieh@gmail.com

      Kindly consider.

      Thanks in advance.

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Hello Qian, I just emailed it to you. Regards, Ann

       

      Author's profile photo Cleber Faria
      Cleber Faria

      Hi Ann,

      It is very encouraging your position in mastering first what is available at SAP standard .
      Thank you for this page.

      I would appreciate if you could send me a copy of the document (PP-MP-DEM).

      (cleber_faria@hotmail.com)

      Thanks

       

       

      Author's profile photo Ann Hustis
      Ann Hustis
      Blog Post Author

      Hi Cleber,

      Just emailed it to you. Regards, Ann

      Author's profile photo Dominic Trevor
      Dominic Trevor

      Thanks for the explanation.

      Can you please share the document as a post or if you can please send it to

      domtrevor.21@gmail.com.. it would be of great help. I am just starting out in SAP Demand management. 🙂

       

       

       

      Author's profile photo Nikos Giannopoulos
      Nikos Giannopoulos

      Hi Ann,

      May I have a copy of the document too, at ngiannopoulos.net@gmail.com?

       

      Best personal regards

      Nikos Giannopoulos

      Author's profile photo Maulik Vania
      Maulik Vania

      Hello Ann,

      Comprehensive explanation  with nicely summarized information.Thank you for sharing.

      Maulik

       

      Author's profile photo N. Pot
      N. Pot

      Hello Ann,

       

      Thanks for sharing this blog. It is very valuable and really helps in understanding this topic.

      I would appreciate if you could send me a copy of the document (PP-MP-DEM).

      (nic_pot@hotmail.com)

      Thanks,

      Nic

       

      Author's profile photo Mathu Thangaraj
      Mathu Thangaraj

      Thanks Ann It is great article  to read how classical MRP can be  solve the problem addressed in  DDMRP. I like to have understand one more point between classical MRP and DDMRP.

      If we have multiple production orders for different products at same day, how classical MRP can prioritize the orders ?  In this case we may need to use scheduling according to sales order due date. But assume next day we have rush order for product with less stock, then we may not be able to deliver the rush order? In this case DDMRP focus on stock level than focusing on due date?

      Also regarding planning strategy, we try to use planning with planning material with dummy BOM and routing, we faced lot of challenges in calculating component QTY and machine QTY. For example if  component requirement for finished material A and B have high difference then it was challenge to maintain component requirement for dummy BOM. Similarly in routing, if machine time varies between the products, then there was challenge in maintaining machine time in dummy BOM. May it is issue with group of materials.

      Author's profile photo Ross Fasco
      Ross Fasco

      Hey Ann,

      Been looking for an article like this as I am thinking along similar lines.  Always pressure in getting the latest and greatest, sometimes we just aren't using what we already have.

      Late to the Blog but if you have that article on the planning strategies, I would appreciate reading this through.  (ross_fasco@agilent.com).  Thanks again.