RIG SAP S/4HANA 1909 Upgrade Document

Introduction:

The following document describes the steps taken for an upgrade to SAP S/4HANA 1909. The source system is our internal RIG test system which was on SAP S/4HANA 1809 with embedded Fiori Front End Server.

The RIG document is available for download here:  SAP S/4HANA 1909 Upgrade 

 

The document includes:

  1. Steps for Maintenance Planner to generate the stack.xml and planning steps.
  2. SUM tool screenshots of each steps along with additional notes and comments we have encountered in our test system.

 

Prerequisite:

We upgraded our HDB 2.0 to the latest revision at the time, which was REV 43. Also, we used SUM Tool version 2.0 SP 6 Patch Level 2

blog1<img />

Source: UPGANA.xml  file

Analysis:

Our SUM Uptime and Downtime timing for this small instance are listed below.

<img />

The total Runtime is 32 hours and 36 minutes while the downtime is 5 hours and 23 minutes. Since this is a test system with a small database and memory footprint, we were able to achieve the weekend downtime with the downtime minimized option.

Longest steps in Downtime = ~ 5 hours  in TABIM_UPG and XPRAS

<img />

Conclusion:

This guide is a reference along with the more detailed Upgrade Guide  to SAP S/4HANA 1909 on premise. Please read both guides before starting your upgrade journey as your system and environment are different.

For planning a system conversion to SAP S/4HANA, please refer to this blog for a great technical overview by our RIG team.

https://blogs.sap.com/2020/05/27/sap-s-4hana-1909-system-conversion-steps-details-how-to-be-prepared/?update=publish

 

Thank you.

RIG

Assigned Tags

      1 Comment
      You must be Logged on to comment or reply to a post.
      Author's profile photo Greg Robinette
      Greg Robinette

      Can transports be moved from S4 1909 FPS00 to S4 1909 FPS01 or FPS02 or 03?