Hi All,
The purpose of this document is to explain how to add the Shifts to the Resource/Work Center Capacities tab,
Prerequisites : Set up the Grouping Key at the Configuration, with the required, Shift Breaks, Shifts Definitions & the Shift sequences, as per the Business requirement.
Follow the below link, for setting up the same. https://wiki.scn.sap.com/wiki/display/ERPMan/How+to+maintain+shifts+for+work+center
Steps to be followed for adding the Shifts, in the Capacities Tab of the Resource/Work Center.
T Code: CRC2 >>>>Go to the Capacity Header Tab

In the next screen that is displayed, Enter the Values for the fields marked 1,2,3
Click on Intervals & Shifts Icon

In the next screen, that displayed,
Click on + Intervals, Button
In the next screen that is displayed
Enter, Valid from & valid to Values, as shown below & Press Enter
In the next screen that is displayed
Keep the Cursor on the Weekday (Ex : MO) & Assign the Last Shift ( Ex : YQS3)
Assign YQS3 & Press Enter
In the Next Screen that is displayed
Keep the Cursor on the Weekday (Ex : MO) & Click on + Shift ( Icon, on the Top)
In the Next Screen, that is displayed
Enter the Additional Shift YQS2 (Above YQS3 Line).
In the Next screen, that is displayed, Keep the Cursor, on the Weekday (MO) & Click on + Shift Icon, to add the new Shift YQS1
In the Next Screen that is played, Enter/Assign YQS1 & Press Enter
Once maintained, you will get the details, like shown below
Follow the same for the remaining Weekdays, by following the sequence, first YQS3, then YQS2, then YQS1
Save the Data >>> This completes the Shifts addition, to the Capacity Tab
Now Check the Available Capacity using the T Code : CM01
*****
Please share your comments/inputs/feedback to make this document as the Most Useful & User-Friendly one.
Thanks & Regards : Raja Sekhara Reddy Bannnuru
Well done Raja. Quite elaborative! Thanks
best regards
Shailesh Mishra
Many Thanks Shaliesh, for your Kind & Encouraging comments
Best Regards : Raja
Hi RAJA SEKHARA REDDY BANNURU
Informative document.Keep going.
Vignesh V
Many Thanks Vignesh for the kind feedback.
Best Regards : Raja
RAJA SEKHARA REDDY BANNURU would like get insights on below
1.How capacity planning is impacting MRP ? in S4 I am not able to see the graph output in form of Gantt Charts.
2.Can two plants with same work centre [ex : WC1 for plant1 & WC1 for plant2] nomenclature handled in capacity planning?
Thank you.
Vignesh.V
Thanks for sharing nice document.
Very detailed explanation.
Thanks
Ramkumar RV
Hi Ram,
Many Thanks for your kind feedback.
Best Regards : Raja
Great read! I have a question. Due to the strict management of higher tier transactions, many of us at our organization do not have OP4A, therefore I could not use grouping for shift definitions. The shifts where created by going into the work center and simply inserting an interval with shifts.
Any concerns with setting up intervals/shifts without using grouping for shift definitions?
Dear RAJA SHEKHAR REDDY BANNNURU
Really this document more helpful for me am before am seeing this document lot of confusion is their in my mind when I go through this document everything will be fine . Thanks a lot keep posting more documents and share your knowledge thank you .
With regards
K JOY
Thanks A Lot for the Kind Feedback & Encouragement.
Best Regards : Raja
Another Level of Explanation
I'm trying to get the information since two days
Thanks a lot
Most Welcome