Customers may want to closely monitor budget overruns and available budget for a few specific cost groups like Travel Costs and Training Costs instead of all costs. This will help them have a better hold over the budget allocated for smaller subset of cost groups and closely monitor the actual costs posted for the same set of cost groups.

With SAP S/4 HANA Cloud 1911, budget-relevant costs can be defined for Projects with the help of Budget Availability Control Profile. This helps  customers in analyzing budget consumption and budget overruns

In order to define costs as budget relevant, a semantic tag needs to be created and the G/L accounts to be categorized as budget relevant must be assigned to this semantic tag. This semantic tag should be assigned to the Budget Availability Control Profile, which will be later associated with the Project. The steps to configure this are explained below.

How to Create a new Semantic Tag

  1. Log on to the Fiori launchpad with the role BPC_EXPERT

  2. Launch the Manage Your Solution app and choose Configure Your Solution

  3. Choose Finance as the Application Area and General Ledger as the Sub Application Area

  4. In the list items retrieved, choose the item with Item Name Chart of Accounts

  5. To create a new semantic tag, select Define Semantic Tag for Financial Statement Version and choose Configure

  6. Choose New Entries, provide all the details and choose Save



How to Associate a Semantic Tag with Items

Prerequisite:

Find out the FSV item number:

  1. Log on to the Fiori launchpad with the role GL_ACCOUNTANT

  2. Launch the Manage Financial Statement Versions app

  3. Select the required Financial Statement Version and choose Financial Statement Items.


Note: In SAP S/4HANA Cloud, the leading Financial Statement Version supported is YPS2. This is associated with A000, the Controlling Area available in SAP S/4HANA Cloud.




  1. Choose Settings and choose Change

  2. Select the checkbox Item Keys Visible and choose Continue to view the FSV item number


Steps to associate a Semantic Tag with FSV Items:

  1. Log on to the Fiori launchpad with the role GL_ACCOUNTANT

  2. Launch the Assign Semantic Tags to FSV app to assign the newly created semantic tag to an FSV Item number that must be defined as budget relevant

  3. Choose New Entries, choose Assign Semantic Tag to FS Item, and choose Continue

  4. Enter the details and choose Save



How to Associate a Semantic Tag with Budget Availability Control Profile

  1. Log on to the Fiori launchpad with the role BPC_EXPERT

  2. Launch the Manage Your Solution app and choose Configure Your Solution

  3. Choose Finance as the Application Area and Overhead Cost Management as the Sub Application Area

  4. In the list items retrieved, choose the item with Item Name Budget Management

  5. To associate a semantic tag with Budget Availability Control Profile, select Maintain Budget Availability Control Profile for Projects and choose Configure

  6. Choose New Entries, and enter the details in Profiles



     7. Select Semantic Tags, and enter the semantic tag created and other details


      8.Select Tolerance Limits, enter the details and choose Save


How to Associate a Budget Availability Control Profile with Project

Associate a budget availability control profile with your projects in the Project Control app and make it Active.


 

How to View the Budget-Relevant Costs in Project Budget Report application

The following AVC columns were introduced to the Project Budget Report – Overview app with SAP S/4HANA Cloud 1911. These columns help users analyze budget-relevant costs defined for a project:

  • Actual Costs (AVC) in Global Currency

  • Commitments (AVC) in Global Currency

  • Planning Category Costs (AVC) in Global Currency

  • Budget (AVC) in Global Currency

  • AVC Assigned Value (AVC Actual + AVC Commitments)

  • Available Budget (AVC Budget - AVC Assigned Value)

  • Actual Costs (AVC) in Project Currency

  • Budget (AVC) in Project Currency

  • Commitments (AVC) in Project Currency

  • Planning Category Costs (AVC) in Project Currency





In the above example, in case of projects that are not mapped to an AVC or mapped to an AVC profile that is still mapped to the ACT_COST semantic tag, then all the costs are displayed in the AVC cost columns.

You can then select one or more projects or WBS elements and choose View Details to navigate to view budget relevant costs at the line item level in the Project Budget Report – Line Items application.

If the Only Budget Relevant Values filter is set to Yes in the Project Budget Report – Line Items screen, then only the budget-relevant costs will be displayed. If the Only Budget Relevant Values filter is set to No, then all costs posted against the project WBS elements will be displayed but non budget-relevant costs will have No as the value in the Budget Relevant Values column


In case of projects that do not have an active budget availability control profile, the Only Budget Relevant Values filter has no influence on the table. All costs related to such projects are displayed in the table. Due to this, even when you set the Only Budget Relevant Values filter to Yes, you will still see line items of these projects in the table. Such line items will have No as the value in the Budget Relevant Values column.

Example of behavior of the Project Budget Report – Overview application

The following configuration is maintained in the system:

G/L Account of Budget Relevant Semantic Tag (Travel Cost & Training Cost) = 10000

G/L Account of Non-Budget Relevant Semantic Tag (Purchased Services) =20000

A project is defined, and the below cost postings are made to it: 
























G/L Account Budget Actual Costs Commitments Planning Category Costs
10000 5000 USD 8000 USD 1000 USD 8000 USD
20000 20000 USD 2000 USD 1000 USD 2000 USD

 

Project Budget Report Overview application will show the below cost details for the three projects:





















Budget in Global Currency Budget (AVC) in Global Currency Actual Costs in Global Currency Actual Costs (AVC) in Global Currency Commitments in Global Currency Commitments (AVC) in Global Currency
Project 25000 USD 5000 USD 10000 USD 8000 USD 2000 USD 1000 USD

 

















Planning Category Costs in Global Currency Planning Category Costs (AVC) in Global Currency Planning Category Costs in Project Currency Planning Category Costs (AVC) in Project Currency
Project 10000 USD 8000 USD 8333.33 EUR 6666.66 EUR

 





















Budget in Project Currency Budget (AVC) in Project Currency Actual Costs in Project Currency Actual Costs (AVC) in Project Currency Commitments in Project Currency Commitments (AVC) in Project Currency
Project 20833.33 EUR 16666.66 EUR 8333.33 EUR 6666.66 EUR 1666.66 EUR 833.33 EUR

 















AVC Assigned Value (AVC Actual + AVC Commitments) Available Budget (AVC Budget - AVC Assigned Value) Assigned Value (Actual + Commitments)
Project 7499.99 EUR 9166.67 EUR 9999.99 EUR

As explained above with this new feature customers can easily monitor accrued costs which are relevant from the allocated Project Budget and Budget Consumption perspective.

This blog post is a first in a series of three. The next topics in the series are:

Project Budget Availability Control Profile - Time Range

Project Budget Availability Control Profile - Budget Currency Type
5 Comments