Technical Articles
Schedule the Background Job as Successor in SAP with BTC EVENT TRIGGER
Hello All,
Hope you are doing well..!!!
Recently, I had requirement for schedule the job in SM37 when second job will start once the first finished. But when you schedule two jobs with a predecessor-successor relationship (start condition “Start after job”), you can schedule the predecessor periodically, but not the successor.
The BTC_EVENT_RAISE program is now available to solve this technical problem.
In this Example, I am going to schedule the job 1 and job 2 where job2 will start once job1 finished.
Steps to be follow is as below:
Step 1) Creating an Event –> Go to Transaction code SM62 –> Select BckProcEvnts tab –> Create an event.
- Go to SM62
Then provide the event name with description.
In the snapshot above we can see I have created an Event ‘Z_TEST’.
Step 2) Creating variant for Program”BTC_EVENT_RAISE”
Go to se38 –> Enter Program name ‘BTC_EVENT_RAISE’—> Select Variant radio Button –> Click Display
Enter a name for Variant and click ‘Create’.
In the following screen, enter the event name, which you have created in SM62 (in Step 1). In my case, I had created ‘ZTEST’ Event.
Click on Attributes, enter description for variant and click on ‘Save’
Step 3:- Create the test job in SM36 as Z_TEST1. (I have given program as RSPO0041 and variant as SAP&001).
Then again, I create the new program and given program name as BTC_EVENT_RAISE and variant as Z_TEST_25 (created in step2). Snapshot FYR.
Now i released the Z_TEST1 and then job automatically started once job 1 completed.
Reference: https://launchpad.support.sap.com/#/notes/919458
Feel free to drop a comment on your thought for SAP Job scheduling methods.
Thanks for reading the blogs and have a safe time ahead..!!