Why Production order disappears from Transaction MD04 and Relevance of Confirmation tab in Production scheduling Profile

This is my first blog post and I will try to address an issue which  has been encountered to me recently where production order was confirmed with final confirmation and order was not fully delivered and system removed this order from MD04 and this lead to Miscalculation in next MRP run.

Issue Illustration:

Example: Let’s Consider a Production order with Quantity of 100 Nos

During Confirmation of this order, User had to do partial confirmation, but he confirmed order with Final confirmation which resulted that this order removed from MD04 with QM lot of 85 Nos and system updated a yield deficit  of 15 Nos in order

 

Once order was confirmed, it disappears from Stock/Requirement list (MD04)

Now, How this Yield Deficit gets updated in order.

This yield deficit gets updated as per design of system that When we finally confirm a quantity smaller than the entire quantity to be confirmed, the difference is transferred to the ‘ExpectYieldVar’ field. (SAP Note: 416774)

The behavior can be changed by updating two flags in Production scheduling Profile (OPKP)

Order has been again posted partially with final confirmation and in this case yield deficit will not get updated. Also Production order with remaining quantity will be available in Stock/Requirement List (MD04)

 

Conclusion:

  1. This behavior is as per standard behavior of SAP as per note 416774 that If we finally confirm a quantity smaller than the entire quantity to be confirmed, the difference is transferred to the ‘ExpectYieldVar’ field.
  2. If order is disappeared from MD04, the quantity in WIP will not be taken into consideration.
  3. If WIP which is yet to confirm, User should do Partial confirmation to avoid such situation.
  4. If we don’t want to update yield deficit in order, we have to do necessary settings in production scheduling profile (OPKP)

 

Thanks…. I hope you will like this blog post.

Any feedback or improvements in blog post will be highly appreciated so that it will be helpful to community members

 

Regards,

Amit Sharma

Assigned Tags

      12 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Deepak Singh
      Deepak Singh

      Nice blog ...Amit  It is very helpful information.

      Author's profile photo Amit Sharma
      Amit Sharma
      Blog Post Author

      Hi

      Thank you Deepak..!!

       

      Regards,

      Amit

      Author's profile photo Samir Sultane
      Samir Sultane

      Dear Amit Sir,

      Very Nicely explained. Many Thanks. But i need more clarification for it because some of the content i did not get.  if possible will you give your Cell Number. Hence we can discuss it in a convenient Way.

       

      My Cell No is 7798820768...

       

      Author's profile photo Amit Sharma
      Amit Sharma
      Blog Post Author

      Hi Samir,

      Thank you..!!

      Kindly directly message me  your queries in inbox here only, i will try to address the same.

       

      Regards,

      Amit

      Author's profile photo Samir Sultane
      Samir Sultane

      Still it would better if we could speak. With out it i can not clear my doubts...

      Author's profile photo Atul Tayade
      Atul Tayade

      Nice blog Amit.

      Author's profile photo Amit Sharma
      Amit Sharma
      Blog Post Author

      Hi,

      Thank you Atul..!!

       

      Regards,

      Amit

      Author's profile photo Rohit Nagdeve
      Rohit Nagdeve

      Very well explained.

      Author's profile photo Amit Sharma
      Amit Sharma
      Blog Post Author

      Hi,

      Thank you Rohit..!!

       

      Regards,

      Amit

      Author's profile photo Abhishek Ashish
      Abhishek Ashish

      Nice Document and well explained

      Author's profile photo Amit Sharma
      Amit Sharma
      Blog Post Author

      Thank you Abhishek..!!

      Author's profile photo Paulo Zaccaro
      Paulo Zaccaro

      Hello Amit, blog very helpful, congrats.

      I did some tests using this concept, and I was successful only when the field "Delivery Completed" in PP order in GR, was disable.

      For that happen, during the confirmation (CO15) I needed disable the field "GR/GI completed" like bellow. Can you check please if in your scenario is the same way ? Tks.

      Regards,

      Paulo Zaccaro