S/4HANA Predictive Material and Resource Planning (pMRP)

Predicative Material and Resource Planning is the new innovation from the S/4HANA application for Cloud and On-promise versions.

The objective of this innovation to identify material availability and resource capacity situations to plan and execute the production process. The early-stage detection of material and capacity constraints will help the planner to make the right decisions to fulfill the customer requirements.

Predictive Material and Resource Planning (pMRP) enables you to create, schedule, and evaluate pMRP simulations that support you in taking informed decisions for your production planning.

You can create and schedule pMRP simulations with your top-level demands and resource constraints. During the simulation creation, the system creates simplified data, based on your forecasted product demand and master data for material- and resource-planning, which is used as reference data in pMRP.

After the creation, you can process and evaluate your simulation. It´s ensured that the number of capacity issues and a delivery performance KPI are constantly up-to-date to enable you to compare your simulated changes so you can assess the impact of changes to your simulation.

Finally, after you decide which simulation is best for your production plan, you can take over the resulting component demand and release it to your operational data as planned independent requirements.

Master Data

There is no specific master data to be created for Predictive Material and Resource Planning. Planners can use production planning master data elements.

  • Material Master
  • BOM
  • Work Center
  • Routing
  • Production Version

Transactional Data:

Planned independent requirements to be entered to initiate the pMRP process.

Key Process Steps

  1. Create planned independent requirements
  2. Schedule pMRP simulation creation
  3. Evaluate and process pMRP simulations
  4. Check and (if desired) apply changes to planned independent requirements

SAP Fiori Apps

  1. Process pMRP Capacity Simulations
  2. Process pMRP Simulations
  3. Schedule pMRP Simulation Creation

With this app you can create multiple simulations, check the impact of simulated changes to capacity or demands on the KPIs, and take informed decisions for your production planning.

Business Benefits

  • Simulate MRP runs to evaluate impacts of possible changes to production plans
  • Helps you create optimized production plans by giving the ability to make informed decisions for changes based on the simulations

Additional Information

https://blogs.sap.com/2019/09/25/predictive-material-and-resource-planning-pmrp/

https://blogs.sap.com/2019/10/30/the-power-of-sap-s4hana-3-predictive-material-and-resource-planning/

https://help.sap.com/viewer/8308e6d301d54584a33cd04a9861bc52/1909.000/en-US/61d3f1634dae44608b46b79e36d77dfb.html

Best Regards,

Lingaiah

Assigned Tags

      15 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Former Member
      Former Member

      Good Explanation on pMRP. can you please share steps to execute pMRP in terms of activation and all

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you very much for your comment Former Member

      I will update the process steps meanwhile you can check the other blog written by Jakob Merlin Frederik Schneller

      https://blogs.sap.com/2019/10/30/the-power-of-sap-s4hana-3-predictive-material-and-resource-planning/

      Author's profile photo Chandramouli P
      Chandramouli P

      Thanks for sharing the information. It's really helpful.

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you!

      Author's profile photo Ravinder Bada Narayana
      Ravinder Bada Narayana

      Good blog thanks for sharing.

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you Ravinder!

      Author's profile photo Prathima Kondeti
      Prathima Kondeti

      Excellent and very Informative.

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you!

      Author's profile photo Suresh Kumar Angara
      Suresh Kumar Angara

      Thanks for sharing the info.

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you Suresh!

      Author's profile photo VARESH N
      VARESH N

      Nice blog.

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you Varesh!

      Author's profile photo venkatasaivijay vasireddy
      venkatasaivijay vasireddy

      Very good blog Lingaiah!

      pMRP is the new topic in the area of planning. Can you explain what is the difference between MRP and pMRP?

      Vijay

      Author's profile photo Lingaiah Vanam
      Lingaiah Vanam
      Blog Post Author

      Thank you Vijay!

      pMRP is a more advanced algorithm compare to classic MRP and overall performance and process improvement.

      Author's profile photo Sergio Perdomo
      Sergio Perdomo

      Hello Lingaiah Vanam,

      I have followed the steps you mentioned, but have a Question on the last Point.
      Once i release the pMRP Simulation. I can see the Status as released but once I go back to the PIR, i dont see that my PIR gets updated… could you please help me to understand that, or what is the outcome of releasing the Simulation?

      thanks a lot!

      Sergio