Re-Explode BOM when convert planned order to production order

Hi for every one,

This blog post about how to re-explode BOM while converting the planned order to production (process) order.

As we know that the system standard behavior when running MRP is to explode BOM in planned order, and when converting this planned order to production order the system doesn’t explode the BOM again but copy the planned order BOM to the production order.

But what if the BOM changed before converting the planned order and we need to consider these changes in production order ?

actually there is a standard solution for this situation.

Follow the path

IMG>>Production>>Shop Floor Control>>Master Data>>Order>>Define order type-dependent parameters

Select your order type

Expand the BOM Explosion

Select option 2 (Read with Newly Determined Explosion Date)

 

Conclusion

**At the time of converting planned order to production order system will act as follow:

Option blank >> the system will not explode the BOM but copy the planned order BOM to production order.

Option 1 >> the system will Re-explode the BOM at the planned order explosion date.

Option 2 >> the system will Re-explode the BOM at the time of conversion if the explotion date in the past.

 

Hope this is useful for you

Thanks

Assigned Tags

      6 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Mohamed Ibrahim
      Mohamed Ibrahim

      Hi Mosbah,

      Thanks for sharing info.

      Keep it up!

       

      Regards,

      Muhamed Ibrahem

      Author's profile photo Abdel Rahman Gamal
      Abdel Rahman Gamal

       

       

      Thank you for knowledge sharing

      Keep it up

       

      Best Regards,

      Author's profile photo Periya Kattuva Sheik
      Periya Kattuva Sheik

      Good Knowledge Sharing

      Author's profile photo Vignesh Veerasamy
      Vignesh Veerasamy

      Hi

      Very useful information.

      Vignesh V

      Author's profile photo Leandro Oliveira
      Leandro Oliveira

      is there a transaction that allows us to make mass modifications, i.e., introduce a component in several BOM's simultaneously?

      Author's profile photo Mosbah Mohamed
      Mosbah Mohamed
      Blog Post Author

      Hi Leandro Oliveira

      If you mean to add a component to several BOMs

      you can use t-codeĀ  CS20