Product Information
SAP PP and PS Integration with Material Component
INTRODUCTION
In this blog post you will learn about integration SAP PP PS with material component.
One of process integration between PP and PS is when you release a project structure (include Work Breakdown Structure, network, and material component) and it will be triggered to production planned order creation.
For detail process will be explained in Main section.
MAIN
If we want to make integration process between SAP PP and PS, we can follow these steps =
- Create project structure include project header, Work Breakdown Structure (WBS), Network, and Material Component (Tcode CJ20N)
- Create WBS Bill of material (Tcode CS71).
- Create Routing (Tcode CA01).In routing header select “material assignment” and input counter routing, material number, plant,and WBS element
- Create cost estimate (Tcode CKW1) and Release cost estimate (Tcode CKW4)
- Release Project ( Tcode CJ20N) and planned order is created automatically.
CONCLUSION
We can make integration process between SAP PP and PS with material component.
This process can be used for production based on project.
Thanks and regards
Anita A.
Hello Anita,
Thanks for sharing ... keep it up
BR
Muhamed
Hi Muhamed,
Thanks for feedback
Regards
Anita
is reservation is planned order ???
i try to create production order from reservation in CO40 but get error planned order not found.
any different configuration for this specific.
please share end to end Documents if you have gaurav.jay.goyal@gmail.com
thanks in Advance
Hi anita
Thanks
hello anita how will create production order ?
is reservation is planned order ???
i try to create production order from reservation in CO40 but get error planned order not found.
any different configuration for this specific.
please share end to end Documents if you have gaurav.jay.goyal@gmail.com
thanks in Advance
.
Hi Gaurav,
If you received the end to end documents then please also share it with me i will be grateful for you.
Regards
Sameed
Is there solution to run the CKW1 collectively?
I'm facing Make to Project scenario. Under a project, many make-level materials are assigned to the Network or the WBS element. I have to run the CKW1 one by one. It's boring.
If there is a transaction which I can run more than 1 material + WBS element, it would be useful.
Thanks in advance.
Linux Gao
Hi,
Did you get the transaction? If yes the please also let me know the transaction it would be helpful for me.
Not yet. Now we have developed a Z-program to automatically run CKW1 in background.