SAP S/4HANA System Conversion: Collective Notes
Hello,
here a short update with regards to the System Conversion Scearion for SAP S/4HANA 1610. We created basically three collective notes, where we collect known important application specific issues s related within the system converion scenario. For 1511 these errors have all been collected within the SUM note. We decided to splitt the collection of these errors in the three phases of the System Conversion Procedure:
1. Application specific notes in system conversion preparation phase
2. Application specific notes in SUM phase
3. Application specific notes in system conversion follow-on phase
Find here the links to these collective notes
PREPARATION Application specific notes in system conversion preparation phase |
2389794 | SAP S/4HANA 1610 – application specific notes in system conversion preparation phase |
SOFWTARE UPDATE MANAGER Application specific notes in SUM phase |
2277083 | Add. info. on converting to SAP S/4HANA using SUM SP18 |
2328543 | Add. info. on converting to SAP S/4HANA using SUM SP19 | |
2377310 | Add. info. on converting to SAP S/4HANA using SUM SP20 | |
FOLLOW-ON Application specific notes in system conversion follow-on phase |
2389807 | SAP S/4HANA 1610 – application specific notes in system conversion follow-on phase |
In case we get aware of additional important application sopecific issues we will add them to these collective notes (depending from the phase where they might occour)
Kind Regards,
Frank
Thanks - This is much awaited and required info.
Also in System conversion-guide & system Upgrade-guide, if a logical sequencing can be checked/reworked, that would be useful.
Regards
MP
Thanks Frank. Much Appreciated.
Regards,
G.V.Shivakkumar