S/4 HANA Migration project Phases
Preparation Phase
- Customize New GL (transition from classic to new GL, if required)
- Customize and activate new Asset Accounting
- Perform period-end closing activities in asset accounting
- Run reconciliation reports to ensure consistent data
- Execute and save financial reports to allow comparison of financial KPI’s after migration
- Assess custom fields that exist in any organization’s existing SAP system
- Collect master data from the customer relating to GL, AA, PC, CC, and IO
- Conduct a workshop to understand the functionality, transactions, and KPIs that the customer would like to accomplish in the migration to SAP S/4HANA Finance
Installation Phase
- Backup totals and index tables which will be made obsolete after SAP S/4HANA Finance migration
- Rename index and total tables into x BCK
- Delete original index and total tables and generate views instead
- Import and activate new programs
- Install all hardware components, web service, and servers
- Install all technical patches as recommended by SAP
- Deploy SAP HANA content
Customizing Phase
- Update ledger configuration
- Verify accounting principles
- Check valuation areas
- Update chart of depreciation
- Update operating concern
- Activate account-based Profitability Analysis
Data Migration Phase
- Migrate New G/L data including cost elements
- Regenerate compatibility views
- Regenerate CO-PA operating concern
- Migrate organization’s line items and balances using the migration framework
- Consistency checks on data
- Perform Smart Financials migration: Fill delta-tables, fill table for AP/AR balances carried forward, perform initial balance carry forward, link line items between CO & FI
Post-Migration Phase
- Create cold store for old index tables
- Update/import FI-AA customizing
- Fill the offsetting account in FI documents
- Run reconciliation reports to check data consistency
- Execute financial reports and compare financial KPI’s with migrated data and KPI’s from the preparation phase
- Perform process tests to ensure successful migration
Testing Phase
- Universal Journal entry posting
- Controlling and Profitability Analysis
- Customer/vendor invoices with payment clearing
- Acquisition and disposal of assets with depreciation run
- Financial closing activities – Smart Financials and analytical reporting
- SAP Fiori Apps—transactional, analytical and KPIs