Auto Usage Decision

If the goods in an inspection lot are confirmed to be free of defects in an inspection, the system can complete an inspection automatically, provided certain prerequisite conditions have been met.

Prerequisite.


The system can only make an automatic usage decision if the following conditions have been met:

  • No characteristic has been rejected in the inspection lot
  • All required characteristics have been confirmed and closed
  • No defect records exist for the inspection lot

Auto UD process is given Below.

Step 1.


SPRO > Quality Management > Maintain Setting at Plant Level.

Au 1.png

In Plant dependent QM setting maintain wait time in Automatic usage decision tab as per the business requirement.

AU2.png

Waiting time :- The number of hours / mins entered here must have expired after creation of the Lot,before the system makes an automatic usage decision for the corresponding inspection lot.

Step 3.

In material master in QM view activate Automatic UD  indicator for the inspection type.

/wp-content/uploads/2016/08/au3_1024072.png


Step 4.


QA01 > Create manual inspection lot for the material.


/wp-content/uploads/2016/08/au4_1024118.png


Inspection lot is created for the material of inspection type 09.


/wp-content/uploads/2016/08/au6_1024119.png


Step 6:-


QE01 > Perform resulting recording .

/wp-content/uploads/2016/08/au7_1024120.png


Result recording is completed for the characteristics.

/wp-content/uploads/2016/08/au8_1024121.png


Result recording is mandatory to perform Auto UD  if required char  indicator is activated for the characteristic.



/wp-content/uploads/2016/08/au9_1024122.png


Step 7

Execute  T-code QA10 to perform Auto UD for the Inspection lot. You can also scheduled job.


/wp-content/uploads/2016/08/au10_1024123.png



Auto UD has been made successfully for the inspection lot.

Au11.png

To report this post you need to login first.

1 Comment

You must be Logged on to comment or reply to a post.

  1. Satish Bhagwat

    Hi,
    I have follow the same step however UD code is not getting update into inspection lot, only status of lot is changed. Please suggest if we need to do something for this as well. 

    (0) 

Leave a Reply