1. How do I schedule a migration?
    • 4.x and 5.x customers
      1. Please complete the 6.x Migration Planning Checklist (Provided by john.lopus@sap.com)
      2. Email john.lopus@sap.com with scheduling requests.
      3. Please include desired timeframe for migration and planned migration type. ie. Manual vs. Assisted (details below).
  2. When will migrations take place?
    • Early Adopter – April through June
    • Scheduling 4.x and 5.x – Starting with July timeslots
  3. How do I learn more about 6.x?
  4. What kinds of “migrations” are there and what are the differences?

/wp-content/uploads/2016/06/2016_06_14_6_36_48_974359.jpg

5.  By when do I need to complete the migration?

    • Goal is to have all customers on 6.x by end of 2016.

6. License or cost implications?

    • No license implications for Test and Production licenses