Purpose of writing this document is sometimes Actual Activity Cost does not get updated in KKBC_ORD against a production order. There are number reasons why activity cost not getting updated for production order as per SAP Note 380282 and the possible reason can be as below -
But I faced updating of Activity Cost in for production order despite maintaining all the parameters above checked and marked.
Everybody can have different cases and solution may vary from case to case as per above points but the problem I faced had solution in below piece of configuration.
Let us see -
Now every time confirmations posted has specific settings maintained in combination with “Order Type and Plant”. This settings is performed here at
Path | SPRO --> SAP Reference IMG --> Production --> Shop Floor Control --> Operations --> Confirmations --> Define Confirmations Parameters |
Transaction Code | OPK4 |
Select relevant order type and plant and click on details button.
Now if you see “SAP1” process control key is maintained for plant and order type.
Process Control Key – Process Control Key determines the execution of confirmations.
Whether confirmation should be updated for operation and order at “Online” OR via “Later in Job”. If you select “Later in Job” you have to run the program subsequently to update the activity cost value via “CORUPROC” and this will update cost and you can see the values in KKBC_ORD report in Actual column.
To see the details of control key you can click on “Overview” button next to process control key description. Also we will see the configuration for control key in next step -
Define time for Confirmation Process –
Path | SPRO --> SAP Reference IMG --> Production --> Shop Floor Control --> Operations --> Confirmations --> Define time for Confirmation Process |
Transaction Code | OPKC |
If SAP1 is already present please check the field “Type” which signifies the type of order it considers for processing of confirmations. Press F4 in “Type” field and you can see below values –
Select relevant order type, in most of the cases it can be “10 – PP Production Order” as it was my case too.
Now next most important part how the “Auto GR”, “Backflush” and “Actual Cost” should update in system.
If you look at the screen shot above 3 options are available –
When selected “Later in Background Job” system saves the confirmation at saving point and stores the values of GR, Backflush and Actual Cost to process in below Tables –
This doesn't update the database as “Actuals”, now to get the actuals; user has to run the report “CORUPROC” which is post processing activity.
Now this setting used where large number confirmation postings are expected during a working hours and this eventually hampers the system performances so all the confirmation postings are processed after business hours via program “CORUPROC”. See below image for program “CORUPROC”
“Immediately Online” is used to update the database and all the relevant tables right after hitting “SAVE” button. As soon as confirmations are saved values can be seen and updated for production order in KKBC_ORD.
In my case “Later In Background Job” was selected and hence value was not updated in order reports and “Actual” always shows ZERO as soon as the option “Immediately Online” selected and saved the setting all the confirmation started showing correct values.
I hope this will help to understand the functionality and solve the issue if anybody facing similar kind of problem.
Thank you for reading the content. Expert’s guiding comments / suggestions are welcome on this.