Skip to Content

This document explains integration between PP module and Plant Maintenance (PM) module

Overview: Integration between PP and PM modules happens during following scenarios…

A) During Capacity Planning for work centers

Already Document has been posted by Our expert Integration between PP module and PM module by Kkumar

B) For tracking the usage value of PRT’s

The below step should be followed for achieving the requirement.

Step 1Create PRT using T.code & Assign Measuring point – IE25/IE01


pastedImage_2.png

Step – 2

Create Measuring Point IK01

Capture.PNG

Step 3


Create a measuring point document with initial counter Reading

Capture.PNG

Step 4

Create the Maintenance plan and counter for the PRT and enter the data.

Creation of Maintenance plan for the PRT (T.code- IP41)

Step 5

Assign the PRT in the routing.

Click on PRT icon

Select the Equipment icon and assign the created PRT to the routing and save it.

Step 6 – Create the Production order for the material using T.code- CO01

Step 7:- Confirm the production order qty using T.code – CO11


Step 8 :- Check the Measurement document of the PRT. [ T.code- IK17 ]

Thanks & Regards

Sandeep Kumar Praharaj

To report this post you need to login first.

6 Comments

You must be Logged on to comment or reply to a post.

  1. Former Member

    Hello every one,

    Its a very good post sandeep sir,good info.However,even when I have followed the above steps as they are given but unfortunately measuring document is not getting generated through production order confirmation.I have spent many hours looking for the solution or any link which i have missed out between these steps….Please help me out with this…Any one with any suggestion are most welcome.

    (0) 
  2. sandeep praharaj Post author

    Hello,

     

    Have you followed all the steps correctly kindly cross check once again still facing issue than contact  any PM consultant avalaible to check the issue.

     

    Thanks

    Sandeep

    (0) 

Leave a Reply