Skip to Content
Author's profile photo Former Member

ChaRM Project Creation in SAP Solution Manager

Dear All,

Here i am giving points to create project successfully for the charm with simple steps to be followed.

For this, in SOLMAN.. Basic configuration, System preparation should be green.

For satellite system Managed system configuration should be completed and READ, TMW and TRUSTED RFCs should be created.

Once this is done.. Go to SOLAR_PROJECT_ADMIN

Select create option..

Maintain a Title and choose a language

Confirm the Pop-Up asking for the document enhancement.

Navigate to the tab System Landscape and select (use value help) the logical component defined before


Navigate to the tab Change Management and activate the Change Management integration for this project. Confirm the pop-up window.


Define a name for the Task List and confirm.

After the successful creation this pop-up will show up.

You can now navigate to the Task List directly. The initial phase value will be Development without Release and the tasks for the project track will still be locked. You can unlock the tasks either by pressing on it with the right mouse button or use the task Lock/Release Transport Tracks incl. Role Types.

Example: Open tasks with task Lock/Release Transport Tracks incl. Role Types

Select the system types for which the tasks should be released and confirm.

After leaving the task list you get directly back to the SAP Solution Manager Project definition. There you can see the successful defined SAP Solution Manager Project which can now be used with Change Request Management.

With this.. Your project creation is completed and you can go ahead with creation of Change Requests with this project.

Regards,

Karthik

Assigned Tags

      Be the first to leave a comment
      You must be Logged on to comment or reply to a post.