We can integrate PM Work Center with HR Work Center in transaction IR02.
PM Work Center Master as below:
PM WC linked to HR WC, as below:
Per the logic, the Cost center in PM WC and CC in PERNR should be same:
The cost center in PERNRs has to be same as Cost center in WC master:
Used WC 1000 in equipment EQUI1000 below:
Created WO: WO1000, using equipment EQUI1000, as below:
We can assign the personnel number at operation level.
Time Confirmation, below. We can again select the PERNR from among the PERNRs already assigned to HR WC for the PM WC. The selected PERNR refers to the person who has performed the actual work. It may be different from the one assigned at operation level.
Cost posted, as below:
Cost posting against the cost center, as below:
Hope it is useful. Any other inputs are welcome.
Good job, thanks for sharing!
Thanks Paul.
Good knowledge sharing Piyush.
Thanks Rao Sir.
Hi Piyush
This is really informative. I had one doubt though.
There is an option of maintaining qualification in the HRMS link. how does it affect the order and the resource selection
Dhanashree
Great Blog, Thank you! Would employee business partners have any impact on this process in S/4HANA? Since employee/personnel number now needs to have a Business Partner linked to it.