We can integrate PM Work Center with HR Work Center in transaction IR02.

/wp-content/uploads/2015/08/1_767396.png

PM Work Center Master as below:

/wp-content/uploads/2015/08/2_767398.png

PM WC linked to HR WC, as below:

/wp-content/uploads/2015/08/3_767399.png

Per the logic, the Cost center in PM WC and CC in PERNR should be same:

/wp-content/uploads/2015/08/4_767400.png

The cost center in PERNRs has to be same as Cost center in WC master:

/wp-content/uploads/2015/08/5_767401.png

/wp-content/uploads/2015/08/6_767405.png

Used WC 1000 in equipment EQUI1000 below:

/wp-content/uploads/2015/08/7_767406.png


Created WO: WO1000, using equipment EQUI1000, as below:

/wp-content/uploads/2015/08/8_767407.png

We can assign the personnel number at operation level.

/wp-content/uploads/2015/08/9_767411.png

/wp-content/uploads/2015/08/10_767412.png

/wp-content/uploads/2015/08/11_767413.png

Time Confirmation, below. We can again select the PERNR from among the PERNRs already assigned to HR WC for the PM WC. The selected PERNR refers to the person who has performed the actual work. It may be different from the one assigned at operation level.

/wp-content/uploads/2015/08/12_767414.png

/wp-content/uploads/2015/08/13_767416.png


Cost posted, as below:

/wp-content/uploads/2015/08/14_767419.png


Cost posting against the cost center, as below:

/wp-content/uploads/2015/08/15_767418.png

Hope it is useful. Any other inputs are welcome.

To report this post you need to login first.

5 Comments

You must be Logged on to comment or reply to a post.

  1. Dhanashree Savant

    Hi Piyush

    This is really informative. I had one doubt though.

    There is an option of maintaining qualification in the HRMS link. how does it affect the order and the resource selection

    Dhanashree

    (0) 

Leave a Reply