跑MRP的时候,就“创建采购申请”有三种选择,1全为采购申请,2未清期间的采购申请,3全为计划订单。“未清期间”在“计划边际码”中设定(SchedMargin key,IMG:Production -> MRP ->
Plan -> 计划和生产参数 -> 定义浮点 ),其解释为:


The number of working days between the date that the order is created and the
planned start date. This time is available for the MRP controller to convert a
planned order into a purchase requisition or a production
order.

也就是计划订单转采购申请/生产订单的提前时间。

md02MRP控制参数/创建采购申请

在事物码:md02中,MRP控制参数/创建采购申请中有两个选择:

1。采购申请 purchase requisition

2。未清期间的采购申请 purchase requisition in opening period

请问他们两者之间有何区别?请举个例子。

对于该问题,系统在计算采购申请的开工日期时,是这样计算的,

首先我们假定采购float的时间为2,某个物料的采购周期为10天,那么在MD02中选择‘1'时,

系统不考虑采购周期和float的问题,所有的需要采购的物料,全部生成采购申请(purchase  requisition

如果选择’2‘,那么系统计算出,需求日期在12天之内(102)的采购供给会被生成为采购申

请,而以后的供给只是以计划订单(planned order)的形式存在。值得注意的是,尽管看的时候

是计划订单,但进去以后会有相关的描述显示该订单是“标准的采购”。

这个意思是说:

1.采购申请:对需采购物料直接创建采购申请,不考虑其它因素.

2.未清期间的采购申请:在未清期间内创建采购申请,在这期间之外创建计划订单,(再由计划订单

转采购申请或生产订单,保持一定的弹性).

3.计划订单:直接创建计划订单,后续再将计划订单转换为采购申请.

我想知道的是如何理解“未清期间”?

假设你的采购申请最晚下达日期为D,采购物料的float时间为D1,做计划的日期为T

如果T < D并且T < D-D1
D属于未清期间。

1、在运行MPSMRP时,创建采购申请和计划行的两个选项都是针对外部采购物料而言的。那么

schedule line中的三个选项和create purchase requisition的三个选项类似,即你考虑的采购申请的计划行的范围。

2、对于planning mode,三个选项分别是,只对计划订单的数量和时间进行简单的调整,重新展bom和工艺路线,删除系统所有的计划订单并重新创建