Enterprise Resource Planning Blogs by Members
Gain new perspectives and knowledge about enterprise resource planning in blog posts from community members. Share your own comments and ERP insights today!
cancel
Showing results for 
Search instead for 
Did you mean: 
sunil_mundhe3
Contributor

Purpose

This step demonstrates how completion confirmations for a production order can influence maintenance measures performed on production resources and tools. This example has been created for a bottling/canning plant. Here, tins are filled with paint. The bottling/canning plant contains a filter press which is recorded as PRT equipment in the task list for material Y-351.The maintenance plan for the PRT equipment contains three performance related maintenance cycles. This means that every time the PRT equipment above is used, different operations are used for the scheduled maintenance plan. In cases of high use this may lead to a change of filter


Data for This Example

Field

Europe

Maintenance plan

40

Material

Y-351

Production plant

1100

Order type

PP01

Total quantity

2000

Basic dates – end

At least four days from now

SchedType

Backwards

Final conf.

Select

Yield to conf.

2000

Measuring Point

10171

Control key

PM01

Component

100-431

Requirement quantity

1

IC (Item category)

L

Sloc

0001

Work center

R_1140

Order type

PM01

Controlling area

1000

Equipment –IE03

Note - (Prerequisits)

  • Equipment should be a PRT
  • Equipment used for Production should have PRT view enable
    • In PRT View
      • Usage Formula should assigned
      • Measuring Point & MP which are used for capturing Reading and scheduling are assigned in this Tab of equipment.

Maintenance Plan – IP03


Note - Before creating MP you should craete Performance Statergy with required Cycles in IP11.

 

Measuring Point –IK01/02/03


Characteristic used is based on production (Unit- Kg)

Creation a Production Order


Use

To create a completion confirmation containing a measurement document, create and confirm a production order.

Procedure

Menu Path

Logistics

® Production ® Production control ® Order ® Create® With material

Transaction Code

CO01

Field

Data

Material

Y-351

Production plant

1100

Order type

PP01

  • Press Enter
  • Enter Following Data

Field

Data

Total quant.

2000

Finish

At least four days from now

Scheduling/Type

Backwards


Production Order – CO03

Operation

Click "PRT" Button

Confirming the Production Order


Menu Path

Production Control

® Confirmation ® Enter ® For order.

Transaction Code

CO15

Field

Data

Final conf.

Select

Yield to conf.

2000

Result

You have confirmed the order. A measuring point was defined as a production resource in the task list, enabling the SAP system to create a measurement document. This document creates a new call after the maintenance plan has been scheduled.

Displaying the Measurement Document

Use

The starting situation for scheduling of production resources and tools (PRT equipment) is displayed.

Procedure

Menu Path

From the Plant Maintenance node, choose Management of Technical Objects ® Equipment ®Measurement Documents ® Display

Transaction Code

IK13

  • Measurement document

Field

Data

Description

Measuring Point

10171

The measuring point is stored in the maintenance plan.

Date to

Today’s date

  • .

You see a list of existing measurement documents.

  • GotoMeasurement document.

This screen allows you to check the data in the completion confirmation for the order.

Ik13

F4

F8

++++++++++++++++++++The End++++++++++++++++++++

4 Comments
Labels in this area