Scope and Effort Analyzer (SEA) in SAP Solution Manager
Using SEA you can check the impact a maintenance event might have on your system. You can check the change impact, how many objects might be affected and which and how many tests have to be carried out. For these purposes a project is created in SEA.
From time to time it happens that no application component hierachy is shown in step 3 (Specify Business Blueprint) during the project creation. These components depend on an entry in table DSWP_CSNCOMP. This entry is created by job SM:GET CSN COMPONENTS. If no entries are shown in this overview check for the above mentioned job.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.