Common issues faced in CHARM implemenation (Version SP12)

I am sharing common issues faced while implementation of charm in SP12.

1. Normal change had status “In development” if it created from the RFC.

Solution

ZMMJ_ON_CREATE_MJ : Define the statuf value in the condition for this action.

/wp-content/uploads/2015/02/image1_646552.png

image 2.PNG

2. Partner id is not visible in Charm approval procedure even after creating the policy.

You need to create the rule moduler profile and assign it here.

image3.PNG

go to Service manager profiles

image4.PNG

Copy as this profile in your own name

image5.PNG

Give the service id as SRV_REQ_RULE_EXE

image6.PNG

In the properties tab, assign the policy that you had created in rule policy through web ui

image7.PNG

3. while extending the scope, release for approval is not visble.

Check the action release for approval and insert the status value and set the maximum value accordingly in the action defination.

image9.PNG

Hope it will be helpfull.

Thanks

Rishav Garg

2 Comments
You must be Logged on to comment or reply to a post.
  • HI Rishav ,

    Getting issue 1 and 2 in SP14 .

    For1 – Have created New action but its not getting picked up and Urgent Change created in Status In development with Developer auto-filled and non editable .

    For2 – Not able to understand the last line assign the policy that you had created in rule policy through web ui  which policy are you referring here??


    Need Help 🙂

    • Hi Aashish,

      What is your scheduled/start condition for the same.

      Policy as approval policy (rule policy) you will create to determine the change manager.

      Thanks

      Rishav