Skip to Content
Author's profile photo Former Member

Progress Analysis with SKF in PS

This document is to briefly explain the way progress of a project/wbs in terms of POC is calculated when planning is performed based on SKF. There is no detail business scenario as this document is mainly to see the steps involved in using the SKF to check the progress of a project.

1. Create SKF

Transactions : KK01/02/03

/wp-content/uploads/2014/12/1_615715.png

Here, the SKF category ‘Fixed Value’ is used. Usually Fixed value is used when the SKF does not change very often, as in the case of number of employees, area etc. The rest of the document will consider the fixed value type of SKF.

2. POC customizing

Transaction : SPRO

  • PS customzing path for progress analysis

/wp-content/uploads/2014/12/2_615770.png

  • Maintain Progress Version

/wp-content/uploads/2014/12/132_653109.png

  • Define Measurement method

/wp-content/uploads/2014/12/3_615771.png

  • Details of Measurement method definition

/wp-content/uploads/2014/12/4_615772.png

3. Cj20n : Progress on WBS

  • Progress version : 132
  • The planned and actual measurement method :MEG_QUANT defined above.
  • The WBS is released and saved.

/wp-content/uploads/2014/12/5_615782.png

Here, both the planned and actual measurement method has been taken as : MEG_QUANT.

4. Posting Planned and Actual SKF

Planning SKF on WBS

If the SKF is defined is a ‘Fixed’ category, then the value of the key figure entered in one month will be used for the remainder of the fiscal year.

If the SKF is defined as a ‘Total’ category, then the value of the key figure entered in one month will be used in one particular month and not the following ones.

In our case SKF – 1304 is Fixed value.

  • Transactions to plan & distribute SKF values on WBS: CJS2/ CJS3.
  • SKF can be planned in CJ20n also on activities & WBS.
  • Transactions to plan & distribute SKF values on network: CJK2/ CJK3.

The below snap shots will show the Planning of SKF on WBS via CJS2

/wp-content/uploads/2014/12/6_615783.png

In CJ20n, the dates tab will have dates which will show the period for which the SKF was planned.

/wp-content/uploads/2014/12/7_615784.png

/wp-content/uploads/2014/12/8_615794.png

Posting actual SKF on WBS

Transaction for posting actual SKF values for WBS is KB31N

/wp-content/uploads/2014/12/9_615796.png

5. Progress Calulation and analysis

Run transaction CNE1 for calculating project progress

/wp-content/uploads/2014/12/10_615800.png
Run Transaction CNE5 for checking the POC for the project

/wp-content/uploads/2014/12/11_615801.png

/wp-content/uploads/2014/12/12_615802.png

Calculations:

Period 7 8 9 10 11 12
        PLAN 100 100
     ACTUAL 50 50 50 50 50 50

POC =              Planned/Actual Quantity    * 100

                       Overall Planned Quantity            

  • POC Actual    = 50/100 * 100   = 50.
  • POC Planned = 100/100 * 100 = 100

6. Reporting SKF Data

Transaction for displaying SKF data both planned & actual is S_ALR_87013548

/wp-content/uploads/2014/12/13_616344.png

On running this standard SAP report

12-30-2014 11-11-43 AM.jpg

The actual and planned SKF values above are the average values across all the periods.

Actual = 50+50+50+50+50+50 / 12 = 300 /12 = 25.

Planned   = 100+ 100 /12   = 200/12  = 16.6667

On drilling down

12-30-2014 11-12-34 AM.jpg

Hope the document will provide an insight into the SKF and progress functionality and how it works in PS. I have mentioned below a few importanat notes which have the recent corrections in the SKF area in PS.

1376215 -Statistical Key Figure – FAQ note

1733126 – SKF functionality is not working correctly in CJ20N

1901566 – SKF- Period distribution incorrect when fiscal variant used

Assigned Tags

      22 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Sammar Razdhan
      Sammar Razdhan

      Nice work Meghana..Maybe at a later stage you can add the business requirements to the document. And other methods as well 🙂 Like Milestones or Time Propotionality

      Author's profile photo Former Member
      Former Member
      Blog Post Author

      Hey Sammar,

      Am sure to work on something you mentioned in the coming year.

      Thanks for your input.

      Author's profile photo Seshagiri Konathala
      Seshagiri Konathala

      Good work Meghana..It will be very useful for the beginners. Keep posting the next document with any Business scenario. All the best.

      Author's profile photo Virendra Shukla
      Virendra Shukla

      Good work Meghana..

      Author's profile photo Former Member
      Former Member
      Blog Post Author

      Thank you All.

      will do better next time.

      Author's profile photo Former Member
      Former Member

      Thanks Meghana,

      Its really a nice document to start on Progress analysis.

      Waiting to see more add-on's on the same,

      Author's profile photo Former Member
      Former Member
      Blog Post Author

      Thank you Vinod.

      Will work on it more.

      Author's profile photo Former Member
      Former Member

      Hi Meghana!  Your document is being very useful! Thanks! I'm a begginer SAP PS and I have some doubts about how maintain progress version. I already created a progress version in transaction SPRO, but it's not working. If you could help me with something... Thanks in advance.

      Author's profile photo Former Member
      Former Member

      The issue has been solved.

      Author's profile photo Cesar Daniel Ramirez Castiblanco
      Cesar Daniel Ramirez Castiblanco

      Hi, Meghana, thanks for your input, at present I´m working with that procedure, however I don´t know if it´s possible that the system calculate the Plan POC on a daily basis with Statical Key Figure

      Thanks in Advance

      Author's profile photo Varshal Kachole
      Varshal Kachole

      Hi,

      Thank you for documenting the Process and the Configuration.

      I would suggest to include the missed out screen print of the Configuration of Progress Version to make this document complete in all aspect.

      Thanks and Regards,

      Varshal Kachole

      Author's profile photo Former Member
      Former Member
      Blog Post Author

      Hello Varshal,

      Thank you for your input.

      I have added the necessary snapshop of the customizing for the progress version.

      Best Regards,

      Meghana.

      Author's profile photo Varshal Kachole
      Varshal Kachole

      Thanks!

      This looks a comprehensive document now.

      Thanks and Regards,

      Varshal Kachole

      Author's profile photo Srinivasan Desingh
      Srinivasan Desingh

      Good job Meghana..

      Author's profile photo Saurabh Tiwari
      Saurabh Tiwari

      Hi Meghna,

      Thanks for sharing this document.

      I replicated the same in my system but found that POC values are not updating in CNE5 report but they are being updated in S_ALR_87013548 report.

      WBS dates were from period 01 to 04 and I planned and posted for these periods.

      Kindly suggest what's missing in that.

      Regards

      Saurabh

      Author's profile photo Abdul K P Kandy
      Abdul K P Kandy

      Its really a Good work.

      Author's profile photo Former Member
      Former Member

      Hi,

      Can any one tell me, how to plan SKF at activity level.

      In Cj20n , i am not able to see SKF tab as mentioned in above doc.

      Author's profile photo Former Member
      Former Member
      Blog Post Author

      Hello Rajiv,

      Please check customizing.

      /wp-content/uploads/2016/06/skf_customzing_978481.jpgYou have to activate the SKF for activity in SPRO for activity...Only then you can view the tab on activity level.

      Regards,

      Meghana.

      Author's profile photo Former Member
      Former Member

      Hi meghana,

      Thanks for ur reply

      I have check SPRO , but these options are not available in my system.

      can you share t-code or any other option.

      Regard

      RAJIV

      Author's profile photo Former Member
      Former Member

      HI Meghna,

      I have activated a business functionality to achieve SKF tab in CJ20n and i have planned SKF at WBS level which i can see on S_ALR_87013548.

      Similarly i have planned SKF at activity level , however i am not able to see the same in S_ALR_87013548.


      Kindly put some light on this issue

      Author's profile photo Kishore JS
      Kishore JS

      Hi,

      Very good document.

      Thanks & Regards

      Kishore

      Author's profile photo tarek kazem
      tarek kazem

      Hi.

      Can anyone tell me why T.Code CNE1 don't run with me?