Key features of run book

  1. We can save the time around 10 Min per day(manually to prepare the run book it takes minimum of 10 min’s per shift)
  2. Details of Process Chains running in each shift that needs to be monitored [along with information on when the chain is supposed to be start].
  3. Ability to send out the Process Chain Status via an e-mail[attachment] if desired to any recipient.
  4. Ability to track the Status of any Process Chain in BW Shift Wise on any particular day. This information is saved in the system so if you want 10 days back status also we can send a mail to desire
    to any recipient.
  5. Ability to track the red Status information. If we have any red status process chain it will provide the
    information why that process chain is red.

Details of Run book program

We have 3 main parts in this program

   1 . Mail

   2 . Process chain status

   3 . Information

Selection screen of the Report:

RUNBOOK.JPG

Detailed Info:

1.Mail:

If we select a mail radio button then the program will send  a mail to recipients like as below

MAIL.JPG

  output

attachment1.JPG

2. Process chain status

If we select a Process chain status radio button then the program will give the present
status of the process chain and if we have any red status it will provide information why that process chain is red.

attachement2.JPG

  Output of the program

attachment3.JPG

attachment4.JPG

If we double click on chain id then the chain will be open if we want to repeat the info package in failed case. We can do that like as below

attachment5.JPG

3. Information

If we select a Information radio button then the program will give the information on when the chain is supposed to be start.

attachment6.JPG

Output of the program

attachment7.JPG

Source code of the program:

Please see the attached notepad.

Please find the below custom tables which I have used for this
requirement.

The below table is used to maintain recipient mail ids.

attachment8.JPG

The below table is used to maintain all process chains and shift types and start time.

attachment9.JPG

The below table is used to save the status of the process chain.

/wp-content/uploads/2014/11/attachment10_589958.jpg

The below table is used to maintain the failed status of the process chain.

/wp-content/uploads/2014/11/attachment11_589959.jpg

Thank you I hope it will be useful for everyone….

To report this post you need to login first.

18 Comments

You must be Logged on to comment or reply to a post.

  1. kolimi moshe

    Hi Anki.

    This is very usefull for filling process chain start time and end time and status to pass other shift consultant like Run Book for support project.

    Good Hard work and thanks.

    Regards

    Moshe.K

    (0) 
  2. kolimi moshe

    Hi Anki.

    This is very usefull for filling process chain start time and end time and status to pass other shift consultant like Run Book for support project.

    Good Hard work and thanks.

    Regards

    (0) 
    1. MOHAMMAD ALTAF RIZVI

      hello Priya,

      I am not able to find any notepad source file with this post.As you mentioned that you have successfully implemented this,so could you please share that document with me.