Automation of shift handover run book
Key features of run book
- We can save the time around 10 Min per day(manually to prepare the run book it takes minimum of 10 min’s per shift)
- Details of Process Chains running in each shift that needs to be monitored [along with information on when the chain is supposed to be start].
- Ability to send out the Process Chain Status via an e-mail[attachment] if desired to any recipient.
- Ability to track the Status of any Process Chain in BW Shift Wise on any particular day. This information is saved in the system so if you want 10 days back status also we can send a mail to desire
to any recipient. - Ability to track the red Status information. If we have any red status process chain it will provide the
information why that process chain is red.
Details of Run book program
We have 3 main parts in this program
1 . Mail
2 . Process chain status
3 . Information
Selection screen of the Report:
Detailed Info:
1.Mail:
If we select a mail radio button then the program will send a mail to recipients like as below
output
2. Process chain status
If we select a Process chain status radio button then the program will give the present
status of the process chain and if we have any red status it will provide information why that process chain is red.
Output of the program
If we double click on chain id then the chain will be open if we want to repeat the info package in failed case. We can do that like as below
3. Information
If we select a Information radio button then the program will give the information on when the chain is supposed to be start.
Output of the program
Source code of the program:
Please see the attached notepad.
Please find the below custom tables which I have used for this
requirement.
The below table is used to maintain recipient mail ids.
The below table is used to maintain all process chains and shift types and start time.
The below table is used to save the status of the process chain.
The below table is used to maintain the failed status of the process chain.
Thank you I hope it will be useful for everyone….
Nice Anki... Good Work 🙂
Help ful 🙂
Nice Doc Polu ... 🙂
Great, will be useful for people in support.
Nice work Anki...Very use full for support projects..
Hi Anki.
This is very usefull for filling process chain start time and end time and status to pass other shift consultant like Run Book for support project.
Good Hard work and thanks.
Regards
Moshe.K
Hi Anki.
This is very usefull for filling process chain start time and end time and status to pass other shift consultant like Run Book for support project.
Good Hard work and thanks.
Regards
Hello kolimi,
I didn't find the notepad document attached with this post.So,could you please share that document with me if you have accessed it.
Useful info...
Hi Anki,
That is Helpfull very much. !! Good one!. status is handed over without possible human errors!!!
Regards
Hi Anki,
This is really good for support projects. It will save much of our time and less chances of human error.
Hi Anki,
Thanks for the info and all you efforts to share the information in sdn.
This is very usefull doc.
Regards,
Bhaskar V
Hi Anki,
Nice Document .The info provided in this doc will surely be very useful to us.
Hi Anki,
We have implemented,working fine.Thanks for the useful info
hello Priya,
I am not able to find any notepad source file with this post.As you mentioned that you have successfully implemented this,so could you please share that document with me.
Nice work Polu keep it up very useful
Hi anki reddy,
It is nice idea,but I didn't find any text attachment of code.
Can you please upload it.
Thanks
Gunateja
Super Anna................!
Regards
VijayMutyala