Issue:  Transferred budget not visible in report CJI8.

Root causeReceiver year not entered in CJ34 when
performing budget transfer between WBS Elements.

Incorrect entry:

Incorrect 1.png

   
  Entry without receiver year.

Incorrect 2a.png

Budget entry flow for posted incorrect document number 100001706

The incorrect posting created inaccurate yearly budget data in report CJI8 for the project.

Incorrect 3.png

 

Incorrect 6.png

To view the entire transfer in CJI8, the report must be executed for Overall values without the year.

Incorrect 5.png

Incorrect 6.png

How To Correct an incorrect budget transfer entry:

To correct the entry, a new entry must be created using a negative dollar value in budget transfer transaction CJ34.  See example below.

Incorrect 7.png

Note the negative value in the Amount column.

Incorrect 8a.png

Budget entry flow for posted document number 100001707

Validate reversal in CJI8

Incorrect 9.png

Incorrect 10.png

NOTE:  

Once the above

steps have been performed the budget transfer must be performed again
correctly.  Be sure to enter year for

Sender and Receiver WBS Element.

This document was generated from the following discussion: Project Budget Transferred not visible in report CJI8 (CJ34)

Assigned Tags

      2 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Saurabh Tiwari
      Saurabh Tiwari

      Hello Tomiya,

      Its a nice document and which contain useful information.

      Good that you posted a document  in SAP PS forum.

      Thanks

      Author's profile photo Former Member
      Former Member
      Blog Post Author

      You are most welcome..I appreciate your note...