How to turn off and on starting a process chain.

Hi,

This document tells how to turn off starting process chain and turn it on again after some time.

Lets suppose the process chain is set to start everyday at 00:01 am and its ready for the next time to run.

It can be checked in RSPC / Process chains / <your PC> / Start process / Displaying Scheduled job(s):

Bez tytułu.png

it should look like this

Bez tytułu.png

or here:

Bez tytułu.png

Bez tytułu.png

(Status “release” means it is active but not running (=waiting for time to start).

Jobs that run in the past and ended have the status “Finished”)

When we have to stop running job or when we are not sure it’s running or not we should terminate selected job.

Bez tytułu.png

When a job has been terminated we can delete the job.

Bez tytułu.png

after deleting the job it should look like this:

Bez tytułu.png

To turn the process chain on again we use / Execution / Schedule (F8)

Bez tytułu.png

we should set priority

Bez tytułu.png

information in a status line can be seen

Bez tytułu.png

Now we may expect the process chain will start as usuall.

What can be checked as above.

Bez tytułu.png

Hope it will help,

Regards, Leszek