Below are the Steps for Configuration for Availability Check in Sales and Distribution Module.
Configurations at IMG level [Basic Functions/TOR & Av. Ch] |
|||
|
Configuration |
Examples/ Remarks |
Description |
01 |
Checking Group |
Ex : 01 for Coll. Req. 02 for Ind. Req. etc. |
Define Checking Group and specify whether check to be carried out and set for Individual/Collective requirements. |
02 |
Requirement Class |
Ex – For Requirement Class 041. |
Switch on Availability Check for the Requirement Class. |
03 |
Schedule Line Category |
Ex : For CP, C1 etc. |
Switch on Availability Check at Schedule Line Category level. |
04 |
Control for Availability Check |
Checking Rules are predefined in SD. Ex : A for SD Order B for SD Delivery etc. |
Assign Checking Rule to Checking Group and define the scope of Availability Check. The scope includes various stock [safety, transfer etc], Inward/Outward movements, RLT etc. |
Other Settings |
|||
01 |
Default Value |
Ex : FERT + Plant1000 = Ch. Gr. 01. |
Checking Group set for [Material Type + Plant ] as default value. Used only if not mentioned in MMR. |
02 |
Material Block |
A –Order, B – Delivery Note, C-Reservation. These initiators cannot be changed. |
Block indicator can be activated if others have to be blocked from carrying out Av. Ch while it is being checked. |
03 |
Item Category |
Ex : REN can be switched off. |
Availability Check can be activated or deactivated at Item Category level. |
04 |
System Responses |
Ex : A dialog box for selecting one time / complete / delevery proposal. |
Based on Sales Area, system responses can be set in Av. Ch. Rule, should there be no/insufficient stock[after Av. Ch]. |