Requirement Prioritization in SAP Materials Management

Summary

This document helps SAP Procurement consultants to understand the requirement prioritization in SAP.

Requirement Prioritization

This function helps to prioritize the requirements based on urgency in Logistics management. This will reduce the lead time from planning to available.

Application

Purchase Requisitions

Requirement urgency can be assigned at item level when creating purchase requisitions manually. The requirement priority will be determined based on requirement urgency. Requirement urgency and requirement priority is interconnected in configuration.

/wp-content/uploads/2013/11/2_330232.png

If you change requirement urgency to next level or another level, requirement priority will also change in accordance with requirement urgency.

/wp-content/uploads/2013/11/3_330251.png

Purchase order

Requirement priority can be assigned when creating automatic purchase order so that the corresponding priority PRs will be selected for conversion. In case of STO, Conversion only takes place if sufficient stock is determined at the issuing storage location in the course of the availability check. When creating manual purchase order, requirement urgency can be assigned at item level.

Via Requisition Assignment List

Transaction code: ME58

Please refer to the below screenshot to know the selection screen for requisition assignment list with requirement priority field.

/wp-content/uploads/2013/11/1_336800.png

Requirement priority “1” assigned Purchase requisitions will be displayed by executing the above transaction (ME58). From there, you can create a purchase order.

/wp-content/uploads/2013/11/5_330261.png

Automatically via Purchase Requisitions

Transaction code: ME59N

Another way of creating creating purchase order automatically is via ME59N. Here on the selection screen input the required priority to be selected and execute the transaction.

Please refer to the below screenshot to know the selection screen for Automatic creation of POs with requirement priority field

/wp-content/uploads/2013/11/2_330232.png

Selected Priority “1” PRs are converted in to POs succesfully.
/wp-content/uploads/2013/11/7_330266.png

As explained previously, requirement priority can be assigned direcly while creating a purchase order. Here, you assign a requirement urgency manually at line item level and the requirement priority will be calculated based on configuration settings.

/wp-content/uploads/2013/11/8_330267.png

The following display shows requirement priority “1” and “4” assigned manually on the purchase order at item level.

/wp-content/uploads/2013/11/9_330268.png

Reservation

Requriement urgency can be assgined to reservation at item level so that requirement priority is determined automatically.

/wp-content/uploads/2013/11/10_330272.png

Via Picking List

Transaction code: MB26

Pick list is used to list down the reservations created for the particular material with reservation quantity. if the reservation is created with the requirement priority then the corresponding reservations will be picked according to the selection criteria (priority 1, etc).

/wp-content/uploads/2013/11/11_330273.png

/wp-content/uploads/2013/11/12_330274.png

Material requirements planning

The requirement priority is determined for purchasing and reservation documents is displayed in the stock/requirements list, in the planning result, and in the MRP list.

/wp-content/uploads/2013/11/13_330275.png

Configuration Overview

Activate Requirement Prioritization

Menu Path:

IMG–>Materials Management–>General Settings for Materials Management–>Requirement Prioritization–> Activate Requirement Prioritization

In this activity, the requirement priority is activated with the combination of requirement priority and requirement urgency. The requirement priority and urgency shall be customized as per business requirement.

/wp-content/uploads/2013/11/14_330277.png

/wp-content/uploads/2013/11/15_330285.png

Define Requirement Urgency Groups

Menu Path:

IMG–>Materials Management–> General Settings for Materials Management–> Requirement Prioritization–> Define Requirement Urgency Groups

Here, urgencies are grouped and defined as requirement urgency groups. Urgency groups shall be defined as low, medium, high. Either alphabetic or numeric shall be used for the definition. Later the requirement urgency groups shall be assigned to the requirement urgency.

/wp-content/uploads/2013/11/17_330289.png

Define and Assign Requirement Urgencies

Menu path:

IMG–>Materials Management–> General Settings for Materials Management–> Requirement Prioritization–> Define and Assign Requirement Urgencies

In this step, create requirement urgency and assign the same to urgency group created in the previous step. Requirement urgency and urgency group have one to one relationship.

/wp-content/uploads/2013/11/3_330251.png

Define Organizational Priorities

Menu path:

IMG–>Materials Management–> General Settings for Materials Management–> Requirement Prioritization–> Define Organizational Priorities

In this step, create organizational priorities. Later, the organizational priorities will be assigned to the plant and storage location. The combination of requirement urgency group and organizational priorities will be determined the required requirement priority.

/wp-content/uploads/2013/11/21_330300.png

Assign Plants and Storage Locations (Optional)

Menu path:

IMG–>Materials Management–> General Settings for Materials Management–> Requirement Prioritization–> Assign Plants and Storage Locations

In this step, assignment of plant and storage location with organizational priority takes place. The assigned organizational priority along with urgency group determined the required requirement priority and defaulted for the plant and storage location. If you assign the organizational priority for the plant and it will be applicable for all the storage location belongs to the plant. If you want to default for a particular storage location, then assign plant and storage location combination for the organizational priority.

/wp-content/uploads/2013/11/23_330302.png

Define Requirement Priorities

Menu path:

IMG–>Materials Management–>General Settings for Materials Management–>Requirement Prioritization–> Define Requirement Priorities

It is the final determination of requirement priority based on the urgency group and the organizational priority. Assignment of urgency group is mandatory here and the organizational priority assignment is optional.

/wp-content/uploads/2013/11/27_330306.png

Assign Delivery Priorities

Menu path:

IMG–>Materials Management–>General Settings for Materials Management–>Requirement Prioritization–>Assign Delivery Priorities

In this step, assign delivery priorities to the combination of requirement priority and requirement urgency. based on this assignment, the requirement priority from the purchase order will be converted in to delivery priority in deliveries. The same will be displayed at item level of the purchase order.

/wp-content/uploads/2013/11/25_330304.png

Assign Order Priorities

Menu path:

IMG–>Materials Management–>General Settings for Materials Management–>Requirement Prioritization–>Assign Order Priorities

In this step, assign the order type (like QM order, PM order) and the priorities to the requirement urgency so that the requirement priority will be determined based on this configuration and used in reservation for the QM, PM orders, etc..

/wp-content/uploads/2013/11/29_330308.png

Conclusion

How the requirement prioritization could be used in supply chain and the configuration part has been explained in a simple and understandable way. Any suggestions towards this document will be always welcome.


Author Bio:

Rifaie.jpg

Mohamed Hasan Rifaie,  a SAP Certified Procurement consultant, is now an employee of Larsen & Toubro Infotech Ltd. He has overall 12 years of experience, out of which more than 6+ years in SAP Consulting (P2P, SRM & WM). He has business experience in various industries like Manufacturing, Electro mechanical Construction and process industries as a Procurement Executive.

Assigned Tags

      9 Comments
      You must be Logged on to comment or reply to a post.
      Author's profile photo Sudip Biswas
      Sudip Biswas

      helpfull

      Author's profile photo Mohamed Ismail
      Mohamed Ismail

      It is very nice document.Thank you mfor sharing.

      with Regards,

      Jaheer

      Author's profile photo Narayana N
      Narayana N

      Hi Rifaie Yusouf,

      Good document. Keep sharing. Thank you.

      Best Regards,

      Narayana N

      Author's profile photo DHARMESH KUMAR VDLAPATLA
      DHARMESH KUMAR VDLAPATLA

      Hi Rifaie Yusouf, Very good Document, Thanks for Sharing Regards Kumar

      Author's profile photo Former Member
      Former Member

      Hi, Nice explanation. I have noticed for service purchase requisition (item cat D) generated from Work Order (external operation) the urgency does not established though the config (as detailed in your post) work with Non stock and stock material. Any idea ?

      Author's profile photo Aaditya Hamine
      Aaditya Hamine

      Very Informative and Interesting Article !

      Thanks for sharing it .

      Regards,

      Aaditya Hamine

      Author's profile photo Kristoffer Pehrson
      Kristoffer Pehrson

      I have seen screen shots of a Requirement Urgency field on component level in PM order. I have searched and searched but I can't find how to activate this. The end user wants to select the Requirement Urgency for each component and not per order

      Author's profile photo Rahul Ramesh
      Rahul Ramesh

      Thanks a lot for the detailed document, Mohamed !

      It's helped me immensely in an implementation project.

      Author's profile photo Houston Giles
      Houston Giles

      Excellent article; thank you.  We have configured Requirement Prioritization to use with our service and maintenance orders.  We are successful in getting the priority of the maintenance order to carry to the reservation, and this priority shows on the reservation element in MD04.  However, when MRP runs and creates a purchase requisiton for the reservation, the resulting purchase requisition does not have the same priority as the reservation, but instead is created with the default priority set in the initial configuration settings when you "Activate Requirement Prioritization".  My question is, should the requirement priority on the reservation carry over to the purchase requisition, or must you also set the priority of the requisition manually after it has been created?