Bex Query: Formula variable using Replacement Path:

We can create formula variable at the bottom of the available operands (key figures listed).

Then assign it to a calculated key-figure or local formula.

/wp-content/uploads/2013/04/slide26_212212.png

Requirement1: To calculate Sales per No. of seats.

Sales value is coming as key figure

No. of seat(characteristic) is attribute of Profit Center and has data-type as NUMC length (4).  

We can not use characteristics in the calculated key figures or in the local formula.

and We need to get the attribute value w.r.to characteristic value of Profit Center (0PROFIT_CTR).

We will convert it into number using formula variable.

We have selected ref. char. as Profit Center and attribute as No. of Seat.

/wp-content/uploads/2013/04/slide20_212228.png/wp-content/uploads/2013/04/slide21_212204.png

/wp-content/uploads/2013/04/slide22_211019.png/wp-content/uploads/2013/04/slide23_211020.png

No of seat has mapping with profit center. We will do exception aggregation with profit center.

Now we can use this CKF to get Sales per Seat.

/wp-content/uploads/2013/04/slide13_210663.png

/wp-content/uploads/2013/04/slide14_210679.png

Output1: /wp-content/uploads/2013/04/slide27_212301.png

  If we use result as summation for Sales per seat, result will be like below:

/wp-content/uploads/2013/04/slide28_212302.png

Output2:/wp-content/uploads/2013/04/slide29_212303.png

Another Scenario: Requirement2:

1.  

         To get term in days = Maturity date(End of Term) – Start date. Where dates are available as characteristics.

         We can create formula variable using replacement path and data-type as date. Create one formula variable for Maturity date and one for Start Date.

         Note the info-object in the reference characterisitcs of general tab.

         for e.g.: total term period, remaining term period can be required in case of Insurance where we have Maturity date,

         start term date, As-of date(evaluation date).

/wp-content/uploads/2013/04/slide07_212211.png   /wp-content/uploads/2013/04/slide08_211737.png

/wp-content/uploads/2013/04/slide09_209740.png/wp-content/uploads/2013/04/slide10_209741.png

Either create Calculated key figure or create a local formula (key-figure Section) to get term in days.

/wp-content/uploads/2013/04/slide16_210937.png

/wp-content/uploads/2013/04/slide17_210956.png

/wp-content/uploads/2013/04/slide19_210958.png

  In   In Requirement1: we have converted info-object:attribute value to number,

        In Requerement2: we have converted Info-object:key value to date.

     