     This is just an attempt to share the concept of MRP run for select-able materials which should undergo planning as per consumption and the reorder point mentioned in the material master. Take the help of ABAPer for performing the following steps.

1. Activate the following exits

EXIT_SAPMM61X_001

EXIT_SAPLM61C_001

2. Check in MD01 screen, new fields called user exit key and user exit parameter will be displayed

Capture.PNG

3. Go to SE37 enter the user exit numbers there

Capture1.PNG

4. Click change and go into the function module and the in the last the following include function will be there

Capture2.PNG

5. Double click on ZXM61U01, write the logic as follows

Capture3.PNG

6. The user exit key is ZVB, user exit parameter is VB and DISMM is MRP type field of material master.

     Create the user exit key in OMIX as shown below

Capture.PNG

7. If you give this user exit in MD01 screen, the system will check the MRP type field of all the materials and plan only the materials which are having VB.

8. Do the same process for the second function module also.

9. The same procedure can be used to run the MRP for MRP controller wise also.

Regards,

Krishna Chandra

To report this post you need to login first.

7 Comments

You must be Logged on to comment or reply to a post.

  1. K Kumar

    Hi,

    These user exits can also be used for planning of materials only with specific material type ?? means I want to plan only materials with Material type FERT in MRP run.

    Can you confirm.

    Thanks

    Kumar

    (0) 

Leave a Reply