Reg:Rollout for SAP Plant Maintenance
Dear experts,
My client needs rollout for sap-pm.they asked to take refernce from the existing plant code.here both planning plant and maintenance plant are same.so in enterprise structure i configured the same.so this order type is copied to the new plant.Is there any other SPRO Settings i have to do?.
Regards,
sathish
Hi,
There are notification type setting, special order type settings, cost display settings, number range settings.....N number of settings there. You have to be specific while asking.
Regards,
Kaushal Rai
Hi,kaushal,
Here we are using the exixting plant code as reference to the new company code.so that all the settings would be copied to the new plant code.Apart from that ,we need to do anything? so can you suggest me wat to do.
sathish
Hi,
I suggest you test the maintenance process with one sample data then you will be aware which customizing setting you missing for now.
Regards,
Kaushal Rai