Dear Experts,

Please explain how to convert the planned orders in mass node in background job because we are not able to run CO41 in background.

Thanks,

Ajay Kumar

To report this post you need to login first.

1 Comment

You must be Logged on to comment or reply to a post.

  1. R Brahmankar

    Dear,

    Please create a discussion for it.

    Use SAP standard program PPBICO40 to convert planned to production orders and program RMCVPLRQ to convert planned orders to purchase reqs.

    Regards,

    R.Brahmankar